Permit Application Status

PREL202001090


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202001090
Electrical
Finaled
DRFC METRO LLC
Alteration/Repair/Replace
PO 36508 DISCONNECT WIRING FOR CONSTRUCTION, DEMO EXISTING FIXTURES, RECYCLE FLUORESCENT LAMPS, WIRE & INSTALL 127 OWNER SUPPLIED 2X4 LED FIXTURES, FURNISH & INSTALL 11 FIXTURES, 6 EXIT/EMERGENCY SIGNS/LIGHTS, 6 OCC SENSORS, 11 SWITCHES, 10 PHONE/DATA OPENINGS, 37 RECEPTACLES, WIRE 1 FURNITURE BASE FEED, 1 RELOCATED VAV BOX.
02/05/2020
02/05/2020
11/16/2020
05/20/2020

Locations

Permits

Permit Number: PREL202001090

Electrical
Finaled
02/05/2020
11/16/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 2/28/2020 (10:00 - 12:00) 2/28/2020 (AM) 02/28/2020
Corrections:


Miscellaneous/Other
Carried Forward
02/28/2020
Phased project- phase one wall RI OK. At ceiling- existing fixture whips. Fasten luminaires to grid per code. Note to general contractor- in areas have abandoned low voltage cable demolished and provide/ maintain independent supported

Electrical Rough-in Inspection Partial Pass 3/13/2020 (12:30 - 2:30) 3/13/2020 (PM) 03/13/2020
Corrections:


Miscellaneous/Other
Carried Forward
03/13/2020
Phased project- phase one wall RI OK. At ceiling- existing fixture whips. Fasten luminaires to grid per code. Note to general contractor- in areas have abandoned low voltage cable demolished and provide/ maintain independent supported

Miscellaneous/Other
Carried Forward
03/13/2020
Above ceiling: inspector left note for general contractor: 1. have all abandoned limited energy cables ( voice/data ) demolished. 2. Temperature control wiring- this scope of work requires electrical permit and inspection. remove/replace all non-plenum cable. 3. provide and maintain support of all existing voice/data cable

Miscellaneous/Other
Carried Forward
03/13/2020
All ceiling tile has not been removed- Replace wiring in makeshift raceway. Pointed out to wireman on the job. There are existing installations - done previously by others- at open tiles support raceways, boxes and MC cable to code.

Miscellaneous/Other
Carried Forward
03/13/2020
Verify egress illumination complies with code- see NEC 700.12

Miscellaneous/Other
Comment Only
03/13/2020
Partial pass above ceiling pending corrections and work by others.

Electrical Rough-in Inspection Partial Pass 3/24/2020 (8:00 - 10:00) 3/24/2020 (AM) 03/24/2020
Corrections:


Miscellaneous/Other
Resolved
03/24/2020
Phased project- phase one wall RI OK. At ceiling- existing fixture whips. Fasten luminaires to grid per code. Note to general contractor- in areas have abandoned low voltage cable demolished and provide/ maintain independent supported

Miscellaneous/Other
Resolved
03/24/2020
Above ceiling: inspector left note for general contractor: 1. have all abandoned limited energy cables ( voice/data ) demolished. 2. Temperature control wiring- this scope of work requires electrical permit and inspection. remove/replace all non-plenum cable. 3. provide and maintain support of all existing voice/data cable

Miscellaneous/Other
Resolved
03/24/2020
All ceiling tile has not been removed- Replace wiring in makeshift raceway. Pointed out to wireman on the job. There are existing installations - done previously by others- at open tiles support raceways, boxes and MC cable to code.

Miscellaneous/Other
Carried Forward
03/24/2020
Verify egress illumination complies with code- see NEC 700.12

Miscellaneous/Other
Comment Only
03/24/2020
Phased project- phase one above ceiling OK

Electrical Final Inspection Partial Pass 3/24/2020 (10:00 - 12:00) 3/24/2020 (AM) 03/24/2020
Corrections:


Miscellaneous/Other
Carried Forward
03/24/2020
Phased project- phase one OK Verify egress lighting is functioning and complies with 700.12

Electrical Rough-in Inspection Partial Pass 4/9/2020 (12:30 - 2:30) 4/9/2020 (PM) 04/09/2020
Corrections:


Miscellaneous/Other
Carried Forward
04/09/2020
Verify egress illumination complies with code- see NEC 700.12

Miscellaneous/Other
Comment Only
04/09/2020
Phase 2 wall RI- at area outside of elevators

Electrical Rough-in Inspection Partial Pass 4/30/2020 (12:30 - 2:30) 4/30/2020 (PM) 05/01/2020
Corrections:


Miscellaneous/Other
Comment Only
05/20/2020
Verify egress illumination complies with code- see NEC 700.12

Miscellaneous/Other
Comment Only
05/20/2020
Partial pass for above ceiling at Phase 2- Met general contractor on the site: one open J- box and CMP HDMI cable laying on ceiling tile. Remove non Plenum rated HDMI cable from ceiling to floor opening Check at next inspection.

Electrical Final Inspection Passed 5/20/2020 (8:00 - 10:00) 5/20/2020 (AM) 05/20/2020
Corrections:


Miscellaneous/Other
Comment Only
05/20/2020
Phased project- phase one OK Verify egress lighting is functioning and complies with 700.12