PREL202003958
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Pending | |||
Electrical Final Inspection | Pending | |||
Electrical Rough-in Inspection | Partial Pass | 10/08/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/08/2020
Met contractor on site- walk thru for UG at building entrance areas and at sleeves
for voice/data installations. ALL OK. progress inspection only.
Call for additional inspections as needed or required.
|
||||
Miscellaneous/Other
Resolved
10/30/2020
void
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/30/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/30/2020
Progress inspection at site for site lighting- OK.
Met contractor on site. Walked through for homeruns and reviewed completed poles- bonding at poles OK.
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/17/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/17/2020
Site visit for site lighting. Progress inspection OK.
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/21/2020 (12:30 - 2:30) | 12/21/2020 (PM) | 12/21/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/21/2020
Inspector note- this is a phased project with the building construction to be performed by two separate electrical contractors under separate permits.
This permit includes the site lighting for the entire project- with the site lighting completion in the summer of 2021.
|
||||
Miscellaneous/Other
Comment Only
12/21/2020
Phase one- of the site lighting approved to the current point of completion.
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/29/2021 (8:00 - 10:00) | 11/29/2021 (AM) | 11/29/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/29/2021
3rd floor partial ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/17/2021 (8:00 - 10:00) | 12/17/2021 (AM) | 12/17/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/17/2021
3rd floor ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/21/2021 (8:00 - 10:00) | 12/21/2021 (AM) | 12/21/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/21/2021
1st floor wall ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/10/2022 (10:00 - 12:00) | 1/10/2022 (AM) | 01/10/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/10/2022
3rd floor wall ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/4/2022 (12:30 - 2:30) | 2/4/2022 (PM) | 02/04/2022 |
Corrections:
Miscellaneous/Other
Comment Only
02/04/2022
1st floor hard lid areas
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/18/2022 (10:00 - 12:00) | 2/18/2022 (AM) | 02/18/2022 |
Corrections:
Miscellaneous/Other
Comment Only
02/18/2022
3rd floor ceiling ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/4/2022 (10:00 - 12:00) | 3/4/2022 (AM) | 03/04/2022 |
Corrections:
Miscellaneous/Other
Comment Only
03/04/2022
2nd floor ceiling ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/18/2022 (10:00 - 12:00) | 3/18/2022 (AM) | 03/18/2022 |
Corrections:
Miscellaneous/Other
Comment Only
03/18/2022
1st floor ceiling ri
|
||||
Electrical Final Inspection | Partial Pass | 4/7/2022 (10:00 - 12:00) | 4/7/2022 (AM) | 04/07/2022 |
Corrections:
Miscellaneous/Other
Comment Only
04/07/2022
3rd floor partial final
|
||||
Electrical Final Inspection | Partial Pass | 4/8/2022 (10:00 - 12:00) | 4/8/2022 (AM) | 04/08/2022 |
Corrections:
Miscellaneous/Other
Comment Only
04/08/2022
3rd floor final
2nd partial final
|
||||
Lighting Inspection | Passed | 05/12/2022 | ||
Electrical Final Inspection | Passed | 5/13/2022 (8:00 - 10:00) | 5/13/2022 (AM) | 05/13/2022 |