PREL202008995
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Pending | |||
Electrical Final Inspection | Failed | 2/10/2021 (8:00 - 10:00) | 2/10/2021 (AM) | 02/10/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
02/10/2021
Left voicemail for contact no call. Drove around building without access or where to go.
|
||||
Electrical Final Inspection | Failed | 2/17/2021 (8:00 - 10:00) | 2/17/2021 (AM) | 02/17/2021 |
Corrections:
Miscellaneous/Other
Resolved
02/17/2021
Left voicemail for contact no call. Drove around building without access or where to go.
|
||||
Miscellaneous/Other
Carried Forward
02/17/2021
New gutter and bus enclosure need to have supply side bonding jumper installed.
|
||||
Electrical Final Inspection | Passed | 3/3/2021 (10:00 - 12:00) | 3/3/2021 (AM) | 03/03/2021 |
Corrections:
Miscellaneous/Other
Resolved
03/03/2021
New gutter and bus enclosure need to have supply side bonding jumper installed.
|
||||
Miscellaneous/Other
Comment Only
03/03/2021
Pictures sent of bonding jumper installed in gutters.
|