Permit Application Status

PREL202009089


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202009089
Electrical
Finaled
AEON VP BLOOMINGTON LLC
Other
WIRE MULTI FAMILY BUILDING - SOLO APARTMENTS BUILDING "A". 1926 E 86th St.
08/17/2020
09/28/2020
02/15/2022
08/20/2021

Locations

Permits

Permit Number: PREL202009089

Electrical
Finaled
09/28/2020
02/15/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Not Ready 11/3/2020 (8:00 - 10:00) 11/3/2020 (AM) 11/03/2020
Corrections:


Miscellaneous/Other
Comment Only
11/03/2020
Inspection scheduled on wrong permit number. There are two buildings: Building A is @1926 East 86th St. Building B is @ 1916 East 86th St. Both buildings are under construction and Collins Electric is the electrical contractor for both projects.

Electrical Rough-in Inspection Partial Pass 1/21/2021 (8:00 - 10:00) 1/21/2021 (AM) 01/22/2021
Corrections:


Miscellaneous/Other
Comment Only
01/22/2021
4th Floor North Phase one- Unit RI OK at # 410, 408, 406, 404, 402, 401, 403, 405, 407, 409. Corridor RI OK. Permit includes fire alarm installations. OK. Elevator & lobby OK.

Electrical Rough-in Inspection Partial Pass 2/1/2021 (8:00 - 10:00) 2/1/2021 (AM) 02/01/2021
Corrections:


Miscellaneous/Other
Comment Only
02/01/2021
RI OK at units # 309, 307, 305, 303, 301, 302, 304, 306, 308 310. RI OK at corridor 3rd floor Phase one- same area as units listed above. Stairwells OK at 3rd and 4th floors. Rooms # 361, 354, 355, 352, 356 RI OK. RI OK at Rooms # 455, 454, 456. Elevator lobby area OK at 3rd and 4th floors.

Electrical Rough-in Inspection Partial Pass 2/10/2021 (8:00 - 10:00) 2/10/2021 (AM) 02/16/2021
Corrections:


Miscellaneous/Other
Comment Only
02/16/2021
1926 East 86th St - Building A ( note address change ) 2nd floor units RI OK Area/zone one- includes the corridor and any common rooms or areas.

Miscellaneous/Other
Comment Only
02/16/2021
Service has been released to Xcel- as have the meters for the apartments.

Electrical Rough-in Inspection Partial Pass 2/19/2021 (10:00 - 12:00) 2/19/2021 (AM) 02/19/2021
Corrections:


Miscellaneous/Other
Comment Only
02/19/2021
RI OK for 1st floor Area A- units and corridor- power and FA Stairwells for area A- OK #126 Community room not ready- call for inspection when complete.

Electrical Rough-in Inspection Partial Pass 3/2/2021 (8:00 - 10:00) 3/2/2021 (AM) 03/03/2021
Corrections:


Miscellaneous/Other
Comment Only
03/02/2021
RI OK for all remaining units on 1st floor includes corridor.

Miscellaneous/Other
Comment Only
03/03/2021
RI OK for all remaining units on 1st floor includes corridor.

Electrical Rough-in Inspection Partial Pass 3/10/2021 (10:00 - 12:00) 3/10/2021 (AM) 03/10/2021
Corrections:


Miscellaneous/Other
Comment Only
03/10/2021
RI OK - 4th floor units and corridor- complete.

Electrical Rough-in Inspection Partial Pass 3/16/2021 (8:00 - 10:00) 3/16/2021 (AM) 03/16/2021
Corrections:


Miscellaneous/Other
Comment Only
03/16/2021
2nd & 3rd floor units, stairs and corridor- RI OK for all

Electrical Rough-in Inspection Partial Pass 3/26/2021 (12:30 - 2:30) 3/26/2021 (PM) 03/26/2021
Corrections:


Miscellaneous/Other
Comment Only
03/26/2021
Above hard lid ceiling RI OK - 1st floor common areas.

Electrical Final Inspection Partial Pass 5/5/2021 (10:00 - 12:00) 5/5/2021 (AM) 05/05/2021
Corrections:


Miscellaneous/Other
Comment Only
05/05/2021
Partial final- final inspection at apartment units. 4th floor units Phase 1 OK.

Electrical Final Inspection Partial Pass 5/6/2021 (12:30 - 2:30) 5/6/2021 (PM) 05/06/2021
Corrections:


Miscellaneous/Other
Comment Only
05/06/2021
Partial pass- 3rd floor units -phase 1 Units OK.

Electrical Rough-in Inspection Partial Pass 05/18/2021
Corrections:


Miscellaneous/Other
Comment Only
05/18/2021
Trench inspections OK for site lighting - RI OK- including trash enclosure

Electrical Final Inspection Partial Pass 05/18/2021
Corrections:


Miscellaneous/Other
Comment Only
05/18/2021
Phase 1, - 2nd floor units- # 201- # 210 final Ok

Electrical Final Inspection Partial Pass 5/19/2021 (Morning) 5/19/2021 (AM) 05/19/2021
Corrections:


Miscellaneous/Other
Comment Only
05/19/2021
Partial final Phase 1 - 1st floor units / 101, 103, 105, 107 all OK

Electrical Final Inspection Partial Pass 06/01/2021
Corrections:


Miscellaneous/Other
Comment Only
06/01/2021
Units OK at remainder of 1st floor -phase 1 ( even side of corridor )

Electrical Final Inspection Partial Pass 06/08/2021
Corrections:


Miscellaneous/Other
Comment Only
06/08/2021
Partial final- 4th floor units complete. Final OK

Electrical Final Inspection Partial Pass 06/09/2021
Corrections:


Miscellaneous/Other
Comment Only
06/09/2021
3rd floor units- final OK- 3rd floor units complete.

Electrical Rough-in Inspection Partial Pass 6/10/2021 (12:30 - 2:30) 6/10/2021 (PM) 06/10/2021
Corrections:


Miscellaneous/Other
Comment Only
06/10/2021
Site visit OK

Electrical Final Inspection Partial Pass 6/23/2021 (Morning) 6/23/2021 (AM) 06/23/2021
Corrections:


Miscellaneous/Other
Comment Only
06/23/2021
Units at 2nd floor final OK. All units 1st -4th floor OK

Electrical Final Inspection Partial Pass 07/23/2021
Corrections:


Miscellaneous/Other
Comment Only
07/23/2021
Lifesafety egress lighting test with building inspector- approved

Electrical Final Inspection Passed 8/17/2021 (12:30 - 2:30) 8/17/2021 (PM) 08/19/2021
Corrections:


Miscellaneous/Other
Comment Only
08/19/2021
All required electrical inspections are complete. Final Inspection- approved. Pending: contractor to verify & document for series rating at three locations.