PREL202009089
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Not Ready | 11/3/2020 (8:00 - 10:00) | 11/3/2020 (AM) | 11/03/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/03/2020
Inspection scheduled on wrong permit number.
There are two buildings: Building A is @1926 East 86th St.
Building B is @ 1916 East 86th St.
Both buildings are under construction and Collins Electric is the electrical contractor for both projects.
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/21/2021 (8:00 - 10:00) | 1/21/2021 (AM) | 01/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/22/2021
4th Floor North Phase one- Unit RI OK at # 410, 408, 406, 404, 402, 401, 403, 405, 407, 409. Corridor RI OK. Permit includes fire alarm installations. OK.
Elevator & lobby OK.
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/1/2021 (8:00 - 10:00) | 2/1/2021 (AM) | 02/01/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/01/2021
RI OK at units # 309, 307, 305, 303, 301, 302, 304, 306, 308 310.
RI OK at corridor 3rd floor Phase one- same area as units listed above.
Stairwells OK at 3rd and 4th floors.
Rooms # 361, 354, 355, 352, 356 RI OK.
RI OK at Rooms # 455, 454, 456.
Elevator lobby area OK at 3rd and 4th floors.
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/10/2021 (8:00 - 10:00) | 2/10/2021 (AM) | 02/16/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/16/2021
1926 East 86th St - Building A ( note address change )
2nd floor units RI OK Area/zone one- includes the corridor and any common rooms or areas.
|
||||
Miscellaneous/Other
Comment Only
02/16/2021
Service has been released to Xcel- as have the meters for the apartments.
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/19/2021 (10:00 - 12:00) | 2/19/2021 (AM) | 02/19/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/19/2021
RI OK for 1st floor Area A- units and corridor- power and FA
Stairwells for area A- OK
#126 Community room not ready- call for inspection when complete.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/2/2021 (8:00 - 10:00) | 3/2/2021 (AM) | 03/03/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/02/2021
RI OK for all remaining units on 1st floor includes corridor.
|
||||
Miscellaneous/Other
Comment Only
03/03/2021
RI OK for all remaining units on 1st floor includes corridor.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/10/2021 (10:00 - 12:00) | 3/10/2021 (AM) | 03/10/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/10/2021
RI OK - 4th floor units and corridor- complete.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/16/2021 (8:00 - 10:00) | 3/16/2021 (AM) | 03/16/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/16/2021
2nd & 3rd floor units, stairs and corridor- RI OK for all
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/26/2021 (12:30 - 2:30) | 3/26/2021 (PM) | 03/26/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/26/2021
Above hard lid ceiling RI OK - 1st floor common areas.
|
||||
Electrical Final Inspection | Partial Pass | 5/5/2021 (10:00 - 12:00) | 5/5/2021 (AM) | 05/05/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/05/2021
Partial final- final inspection at apartment units.
4th floor units Phase 1 OK.
|
||||
Electrical Final Inspection | Partial Pass | 5/6/2021 (12:30 - 2:30) | 5/6/2021 (PM) | 05/06/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/06/2021
Partial pass- 3rd floor units -phase 1
Units OK.
|
||||
Electrical Rough-in Inspection | Partial Pass | 05/18/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/18/2021
Trench inspections OK for site lighting - RI OK- including trash enclosure
|
||||
Electrical Final Inspection | Partial Pass | 05/18/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/18/2021
Phase 1, - 2nd floor units- # 201- # 210 final Ok
|
||||
Electrical Final Inspection | Partial Pass | 5/19/2021 (Morning) | 5/19/2021 (AM) | 05/19/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/19/2021
Partial final Phase 1 - 1st floor units / 101, 103, 105, 107 all OK
|
||||
Electrical Final Inspection | Partial Pass | 06/01/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/01/2021
Units OK at remainder of 1st floor -phase 1 ( even side of corridor )
|
||||
Electrical Final Inspection | Partial Pass | 06/08/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/08/2021
Partial final- 4th floor units complete. Final OK
|
||||
Electrical Final Inspection | Partial Pass | 06/09/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/09/2021
3rd floor units- final OK- 3rd floor units complete.
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/10/2021 (12:30 - 2:30) | 6/10/2021 (PM) | 06/10/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/10/2021
Site visit OK
|
||||
Electrical Final Inspection | Partial Pass | 6/23/2021 (Morning) | 6/23/2021 (AM) | 06/23/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/23/2021
Units at 2nd floor final OK.
All units 1st -4th floor OK
|
||||
Electrical Final Inspection | Partial Pass | 07/23/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/23/2021
Lifesafety egress lighting test with building inspector- approved
|
||||
Electrical Final Inspection | Passed | 8/17/2021 (12:30 - 2:30) | 8/17/2021 (PM) | 08/19/2021 |
Corrections:
Miscellaneous/Other
Comment Only
08/19/2021
All required electrical inspections are complete.
Final Inspection- approved.