PREL202009090
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 11/03/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/03/2020
Building A- met contractor on-site.
Walk through of underground/trenching at the parking garage for Building A.
Walk through OK.
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/9/2020 (2:30 - 3:30) | 12/9/2020 (PM) | 12/09/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/09/2020
1926 East 86th- Building B.
400 AMP OH 120/240 volt single phase temp service for construction
OK to release to Xcel.
|
||||
Electrical Rough-in Inspection | Partial Pass | 03/02/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/02/2021
Progress inspection- UG OK at parking garage.
|
||||
Electrical Rough-in Inspection | Partial Pass | 5/17/2021 (10:00 - 12:00) | 5/17/2021 (AM) | 05/17/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/17/2021
4th Floor units RI OK- Phase 1 West
|
||||
Electrical Rough-in Inspection | Partial Pass | 5/26/2021 | 5/26/2021 (AM) | 05/27/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/27/2021
RI OK for remaining units Phase 1 at 4th floor.
RI OK for Phase 1 - 3rd units.
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/10/2021 (8:00 - 10:00) | 6/10/2021 (AM) | 06/10/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/10/2021
RI OK at 2nd floor units -for Phase one.
|
||||
Miscellaneous/Other
Comment Only
06/10/2021
Service OK to be released to Xcel- 120/208 1600 amp & 120/208 600 amp.
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/17/2021 (Afternoon) | 6/17/2021 (PM) | 06/17/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/17/2021
Partial- RI of Phase one units as signed off at the units.
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/21/2021 (10:00 - 12:00) | 6/21/2021 (AM) | 06/21/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/21/2021
RI OK at remaining units phase one 1st floor.
RI OK at common areas phase one 1st through 4th floor.
Corridor RI OK.
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/23/2021 (Afternoon) | 6/23/2021 (PM) | 06/23/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/23/2021
1st floor common areas- RI OK
1st floor phase 2 units- partial OK for units that were complete- see sign off at door jambs.
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/8/2021 (10:00 - 12:00) | 7/8/2021 (AM) | 07/08/2021 |
Corrections:
Miscellaneous/Other
Comment Only
07/08/2021
4th floor units RI OK- complete.
4th floor corridor and all stairwells RI OK -complete
3rd Floor units RI OK phase 2 except for end two units- see signoff at door jambs.
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/15/2021 (10:00 - 12:00) | 7/15/2021 (AM) | 07/15/2021 |
Corrections:
Miscellaneous/Other
Comment Only
07/15/2021
3rd floor RI OK - units and complete.
2nd flor RI OK - units and complete.
1st floor RI - units as signed off on door card.
|
||||
Miscellaneous/Other
Comment Only
07/15/2021
Progress inspection at site lighting- OK
|
||||
Electrical Rough-in Inspection | Passed | 7/23/2021 (8:00 - 10:00) | 7/23/2021 (AM) | 07/23/2021 |
Corrections:
Miscellaneous/Other
Comment Only
07/23/2021
RI OK for remaining units on 1st floor
RI complete for building
|
||||
Electrical Rough-in Inspection | Passed | 8/13/2021 (8:00 - 10:00) | 8/13/2021 (AM) | 08/13/2021 |
Corrections:
Miscellaneous/Other
Comment Only
08/13/2021
RI OK at 1st floor common areas ceilings
All RI inspections for the building are complete and approved
|
||||
Electrical Final Inspection | Partial Pass | 09/20/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/20/2021
Site visit/progress inspection.
|
||||
Electrical Final Inspection | Partial Pass | 9/21/2021 (10:00 - 12:00) | 9/21/2021 (AM) | 09/21/2021 |
Corrections:
Miscellaneous/Other
Comment Only
09/21/2021
4th Floor units- west: final OK to elevator lobby.
Verbal for breaker lock off at hardwired "range" in ADA unit.
|
||||
Electrical Final Inspection | Partial Pass | 9/23/2021 (8:00 - 10:00) | 9/22/2021 (AM) | 09/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
09/22/2021
3rd Floor west- units / final OK to elevator lobby.
|
||||
Electrical Final Inspection | Partial Pass | 9/23/2021 (10:00 - 12:00) | 9/23/2021 (AM) | 09/23/2021 |
Electrical Final Inspection | Partial Pass | 9/23/2021 (8:00 - 10:00) | 9/23/2021 (AM) | 09/23/2021 |
Corrections:
Miscellaneous/Other
Comment Only
09/23/2021
2nd floor west units / final OK - up to elevator lobby
Verbal- check DW circuit at unit 222
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/24/2021 (Morning) | 9/24/2021 (AM) | 09/24/2021 |
Corrections:
Miscellaneous/Other
Comment Only
09/24/2021
1st floor units- west to elevator lobby -final OK.
Except unit 124- which is being used temporarily as the general contractors office- inspect prior to final occupancy.
|
||||
Electrical Final Inspection | Partial Pass | 10/21/2021 (Morning) | 10/21/2021 (AM) | 10/21/2021 |
Corrections:
Miscellaneous/Other
Comment Only
10/21/2021
Progress final inspection.
4th Floor units- final complete.
|
||||
Electrical Final Inspection | Partial Pass | 10/27/2021 (12:30 - 2:30) | 10/27/2021 (PM) | 10/27/2021 |
Final Inspection on 2nd floor as per contractor | ||||
Corrections:
Miscellaneous/Other
Comment Only
10/27/2021
Progress inspection OK
|
||||
Electrical Final Inspection | Partial Pass | 11/01/2021 | ||
Corrections:
Miscellaneous/Other
Resolved
11/02/2021
Progress inspections-
Units on 4th & 3rd- final complete.
!/2 units on 2nd floor -south final OK.
Verbal for breaker lock off at hardwired cooktop.
|
||||
Miscellaneous/Other
Comment Only
11/01/2021
All units 2nd, 3rd & 4th floors Final OK
|
||||
Electrical Final Inspection | Partial Pass | 11/01/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/01/2021
Units on 4th, 3rd and 2nd floors all OK- final OK for these areas.
|
||||
Electrical Rough-in Inspection | Passed | 11/10/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/10/2021
ALL RI inspections completed
|
||||
Electrical Final Inspection | Partial Pass | 11/10/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/10/2021
Egress lighting walk through- approved.
Verbal add one EM light at stair and lower Exit sign at parking ramp
|
||||
Electrical Final Inspection | Partial Pass | 11/15/2021 (12:30 - 2:30) | 11/15/2021 (PM) | 11/15/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/15/2021
1st floor east- Units final inspection OK
|
||||
Electrical Final Inspection | Passed | 11/16/2021 (8:00 - 10:00) | 11/16/2021 (AM) | 11/16/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/16/2021
Final inspection complete.
Approved.
|