PREL202009117
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 10/8/2020 (8:00 - 10:00) | 10/8/2020 (AM) | 10/08/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/08/2020
Grounding for service- ok
|
||||
Electrical Rough-in Inspection | Passed | 11/23/2021 (8:00 - 10:00) | 11/23/2021 (AM) | 11/23/2021 |
Electrical Final Inspection | Passed | 11/23/2021 (8:00 - 10:00) | 11/23/2021 (AM) | 11/23/2021 |