PREL202010290
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 10/12/2020 (8:00 - 10:00) | 10/12/2020 (AM) | 10/12/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/12/2020
Questions at site- location of PV disconnect.
|
||||
Electrical Rough-in Inspection | Not Ready | 11/3/2020 (Afternoon) | 11/3/2020 (PM) | 11/03/2020 |
Corrections:
Miscellaneous/Other
Resolved
11/03/2020
rescheduled to 11/04/2020
|
||||
Electrical Rough-in Inspection | Passed | 11/4/2020 (8:00 - 10:00) | 11/4/2020 (AM) | 11/05/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/05/2020
RI OK- met on site to review distribution/disconnects and feeders.
ALL OK. Need roof access at final inspection.
|
||||
Electrical Final Inspection | Passed | 11/17/2020 (8:00 - 10:00) | 11/17/2020 (AM) | 11/17/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/17/2020
Met contractor on-site. Roof was snow covered.
Final OK. Minor items with conduit support- one location and complete labeling at second "service" disconnect. contractor contact to email photos to inspector when completed.
|