Permit Application Status

PREL202010435


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202010435
Electrical
Finaled
AMIRA INSPIRE BLOOMINGTON LLC
Other
Complete electrical systems for 133-unit apt bldg, including wiring for temp control and fire alarm
09/10/2020
10/09/2020
06/05/2022
12/07/2021

Locations

Permits

Permit Number: PREL202010435

Electrical
Finaled
10/09/2020
06/05/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 12/22/2020 (12:30 - 2:30) 12/22/2020 (PM) 12/22/2020
Corrections:


Miscellaneous/Other
Carried Forward
12/22/2020
Partial underground

Electrical Rough-in Inspection Partial Pass 12/30/2020 (12:30 - 2:30) 12/30/2020 (PM) 12/30/2020
Corrections:


Miscellaneous/Other
Carried Forward
12/30/2020
Partial underground

Miscellaneous/Other
Carried Forward
12/30/2020
Underground ri

Electrical Rough-in Inspection Partial Pass 1/25/2021 (10:00 - 12:00) 1/25/2021 (AM) 01/25/2021
Corrections:


Miscellaneous/Other
Carried Forward
01/25/2021
Partial underground

Miscellaneous/Other
Carried Forward
01/25/2021
Underground ri

Miscellaneous/Other
Carried Forward
01/25/2021
Temp power 1st floor

Electrical Rough-in Inspection Partial Pass 4/7/2021 (10:00 - 12:00) 4/7/2021 (AM) 04/08/2021
Corrections:


Miscellaneous/Other
Carried Forward
04/12/2021
Partial underground

Miscellaneous/Other
Carried Forward
04/12/2021
Underground ri

Miscellaneous/Other
Carried Forward
04/12/2021
Temp power 1st floor

Miscellaneous/Other
Carried Forward
04/12/2021
5th floor east ri

Electrical Rough-in Inspection Partial Pass 4/12/2021 (10:00 - 12:00) 4/12/2021 (AM) 04/12/2021
Corrections:


Miscellaneous/Other
Outstanding
04/12/2021
5th floor center unit ri

Electrical Rough-in Inspection Partial Pass 4/19/2021 (10:00 - 12:00) 4/19/2021 (AM) 04/19/2021
Corrections:


Miscellaneous/Other
Carried Forward
04/26/2021
Partial underground

Miscellaneous/Other
Carried Forward
04/26/2021
Underground ri

Miscellaneous/Other
Carried Forward
04/26/2021
Temp power 1st floor

Miscellaneous/Other
Carried Forward
04/26/2021
5th floor east ri

Miscellaneous/Other
Carried Forward
04/26/2021
4th floor east ri

Electrical Rough-in Inspection Partial Pass 4/26/2021 (10:00 - 12:00) 4/26/2021 (AM) 04/26/2021
Corrections:


Miscellaneous/Other
Carried Forward
05/03/2021
4th floor center area East 1200amp service ok

Electrical Rough-in Inspection Partial Pass 5/3/2021 (10:00 - 12:00) 5/3/2021 (AM) 05/03/2021
Corrections:


Miscellaneous/Other
Outstanding
04/26/2021
Partial underground

Miscellaneous/Other
Outstanding
04/26/2021
Underground ri

Miscellaneous/Other
Outstanding
04/26/2021
Temp power 1st floor

Miscellaneous/Other
Outstanding
04/26/2021
5th floor east ri

Miscellaneous/Other
Outstanding
04/26/2021
4th floor east ri

Miscellaneous/Other
Outstanding
05/03/2021
3rd floor east ri Service inspection

Electrical Rough-in Inspection Partial Pass 5/5/2021 (8:00 - 10:00) 5/5/2021 (AM) 05/05/2021
Corrections:


Miscellaneous/Other
Carried Forward
05/10/2021
4th floor center area East 1200amp service ok

Miscellaneous/Other
Carried Forward
05/10/2021
3rd floor center area ri

Electrical Rough-in Inspection Partial Pass 5/10/2021 (10:00 - 12:00) 5/10/2021 (AM) 05/10/2021
Corrections:


Miscellaneous/Other
Outstanding
05/10/2021
2nd floor east ri

Electrical Rough-in Inspection Partial Pass 5/17/2021 (10:00 - 12:00) 5/17/2021 (AM) 05/17/2021
Corrections:


Miscellaneous/Other
Outstanding
05/10/2021
4th floor center area East 1200amp service ok

Miscellaneous/Other
Outstanding
05/10/2021
3rd floor center area ri

Miscellaneous/Other
Comment Only
05/17/2021
1st floor east

Electrical Rough-in Inspection Partial Pass 5/24/2021 (10:00 - 12:00) 5/24/2021 (AM) 05/24/2021
Corrections:


Miscellaneous/Other
Comment Only
05/24/2021
2nd floor common area’s 5th floor ri west side

Electrical Rough-in Inspection Partial Pass 6/1/2021 (10:00 - 12:00) 6/1/2021 (AM) 06/01/2021
Corrections:


Miscellaneous/Other
Comment Only
06/01/2021
4th floor west ri

Electrical Rough-in Inspection Passed 6/7/2021 (10:00 - 12:00) 6/7/2021 (AM) 06/07/2021
Corrections:


Miscellaneous/Other
Comment Only
06/07/2021
3rd floor west ri

Electrical Rough-in Inspection Partial Pass 6/14/2021 (10:00 - 12:00) 6/14/2021 (AM) 06/14/2021
Corrections:


Miscellaneous/Other
Carried Forward
06/21/2021
2nd floor ri west

Electrical Rough-in Inspection Passed 6/21/2021 (10:00 - 12:00) 6/21/2021 (AM) 06/21/2021
Corrections:


Miscellaneous/Other
Outstanding
06/21/2021
1st floor west ri

Electrical Rough-in Inspection Partial Pass 6/29/2021 (10:00 - 12:00) 6/29/2021 (AM) 06/29/2021
Corrections:


Miscellaneous/Other
Carried Forward
06/29/2021
2nd floor ri west

Miscellaneous/Other
Comment Only
06/29/2021
Pool bonding shell only

Electrical Rough-in Inspection Partial Pass 7/13/2021 (8:00 - 10:00) 7/13/2021 (AM) 07/13/2021
Corrections:


Miscellaneous/Other
Carried Forward
07/13/2021
2nd floor ri west

Miscellaneous/Other
Carried Forward
07/13/2021
Crossover wall ri

Electrical Final Inspection Partial Pass 9/1/2021 (12:30 - 2:30) 7/28/2021 (AM) 07/28/2021
Corrections:


Miscellaneous/Other
Comment Only
07/28/2021
522-530 final ok

Electrical Rough-in Inspection Partial Pass 8/18/2021 (12:30 - 2:30) 8/18/2021 (PM) 08/18/2021
Corrections:


Miscellaneous/Other
Carried Forward
08/18/2021
2nd floor ri west

Miscellaneous/Other
Carried Forward
08/18/2021
Crossover wall ri

Miscellaneous/Other
Comment Only
08/18/2021
Crossover ceiling ri

Electrical Final Inspection Partial Pass 9/1/2021 (12:30 - 2:30) 9/1/2021 (PM) 09/01/2021
Corrections:


Miscellaneous/Other
Comment Only
09/01/2021
5th and 4th east final

Electrical Rough-in Inspection Passed 9/8/2021 (12:30 - 2:30) 9/8/2021 (PM) 09/08/2021
Corrections:


Miscellaneous/Other
Outstanding
08/18/2021
2nd floor ri west

Miscellaneous/Other
Outstanding
08/18/2021
Crossover wall ri

Miscellaneous/Other
Comment Only
09/08/2021
Pool bonding ok Underground front exterior ok

Electrical Final Inspection Partial Pass 9/22/2021 (12:30 - 2:30) 9/22/2021 (PM) 09/22/2021
Corrections:


Miscellaneous/Other
Comment Only
09/22/2021
3rd floor east final ok 2nd floor east partial final

Electrical Final Inspection Partial Pass 9/29/2021 (12:30 - 2:30) 9/29/2021 (PM) 09/29/2021
Corrections:


Miscellaneous/Other
Comment Only
09/29/2021
2nd floor east final ok 1st floor east partial final

Electrical Final Inspection Partial Pass 10/28/2021 (8:00 - 10:00) 10/28/2021 (AM) 10/28/2021
Corrections:


Miscellaneous/Other
Comment Only
10/28/2021
5th floor west finals

Lighting Inspection Partial Pass 11/2/2021 11/02/2021
Parking garage inspection. Lighting exceeded City Code requirements. Lighting not yet installed immediately inside overhead garage door. Contractor to notify Planning when lights are installed.
Lighting Inspection Passed 11/4/2021 11/04/2021
Lighting has been installed inside garage door.
Electrical Final Inspection Failed 11/4/2021 (10:00 - 12:00) 11/4/2021 (AM) 11/04/2021
Corrections:


Miscellaneous/Other
Comment Only
11/04/2021
Inspection cancelled

Electrical Final Inspection Partial Pass 11/10/2021 (12:30 - 2:30) 11/10/2021 (PM) 11/10/2021
Corrections:


Miscellaneous/Other
Comment Only
11/10/2021
4th floor west final ok

Lighting Inspection Partial Pass 11/15/2021 11/10/2021
Parking garage inspection. Lighting exceeded City Code requirements. Lighting not yet installed immediately inside overhead garage door. Contractor to notify Planning when lights are installed.
Electrical Final Inspection Partial Pass 11/16/2021 (12:30 - 2:30) 11/16/2021 (PM) 11/16/2021
Corrections:


Miscellaneous/Other
Comment Only
11/16/2021
1st floor common area’s final

Electrical Final Inspection Partial Pass 11/22/2021 (10:00 - 12:00) 11/22/2021 (AM) 11/22/2021
Corrections:


Miscellaneous/Other
Comment Only
11/22/2021
3rd floor west final ok

Electrical Final Inspection Partial Pass 11/23/2021 (12:30 - 2:30) 11/23/2021 (PM) 11/23/2021
Corrections:


Miscellaneous/Other
Comment Only
11/23/2021
Basement final EM lights ok all floors

Electrical Final Inspection Partial Pass 12/1/2021 (8:00 - 10:00) 12/1/2021 (AM) 12/01/2021
Corrections:


Miscellaneous/Other
Comment Only
12/01/2021
2nd floor partial final

Electrical Final Inspection Partial Pass 12/2/2021 (8:00 - 10:00) 12/2/2021 (AM) 12/02/2021
Lighting Inspection Passed 12/6/2021 12/06/2021
Exterior lighting inspected 12.2.21. Passed inspection - inspection report printed to building permit documents.
Electrical Final Inspection Passed 12/7/2021 (10:00 - 12:00) 12/7/2021 (AM) 12/07/2021