Permit Application Status

PREL202011737


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202011737
Electrical
Finaled
THE LUTHER COMPANY LLLP
Other
Installation and wiring for a new Solar Photovoltaic system.
09/30/2020
02/17/2021
08/23/2021
02/24/2021

Locations

Permits

Permit Number: PREL202011737

Electrical
Finaled
02/17/2021
08/23/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Final Inspection Passed 2/23/2021 (2:30 - 3:30) 2/23/2021 (PM) 02/24/2021
Inspection moved. Contractor won't be ready on Friday.
Corrections:


Miscellaneous/Other
Comment Only
02/24/2021
Solar install- ok Xcel contacted.