PREL202011846
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 10/14/2020 (12:30 - 2:30) | 10/14/2020 (PM) | 10/15/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/15/2020
Progress inspection: at transformer installation: verbal- provide supply side bonding jumpers to code.
At MTW conductors- provide listed terminations for finely stranded conductors.
At power supply distribution; 12 current carrying conductor requires derating of 50%.
Call for additional inspections.
Verify listing/labeling or independent 3rd party evaluations as required.
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/21/2020 (10:00 - 12:00) | 10/21/2020 (AM) | 10/22/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/22/2020
Walk through tools with contractor on-site.
Wiring to tools OK.
Verify GEC requirements with owner for the Endura 501 tool.
|
||||
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified
Carried Forward
10/22/2020
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified.
Unlisted equipment requires independent 3rd party evaluation.
See email correspondence with contractor and owners rep & 3rd party engineers.
|
||||
Electrical Rough-in Inspection | Not Ready | 02/08/2021 | ||
Corrections:
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified
Carried Forward
02/08/2021
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified.
Unlisted equipment requires independent 3rd party evaluation.
See email correspondence with contractor and owners rep & 3rd party engineers.
|
||||
Electrical Final Inspection | Passed w/ Conditions | 02/15/2022 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/15/2022
Tools evaluated by PE
PE does not have access to permit numbers - as such several contractors have permits for tool hook-ups.
Evaluation reports are difficult to associate with a particular permit number.
All tools bear field label indicating the report number.
|