Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Final Inspection | Failed | 10/28/2020 | ||
Corrections:
Miscellaneous/Other
Carried Forward
10/28/2020
Site contact not available- reschedule and call for re-inspection.
|
||||
Electrical Final Inspection | Failed | 11/2/2020 (8:00 - 10:00) | 11/2/2020 (AM) | 11/02/2020 |
Corrections:
Miscellaneous/Other
Resolved
11/02/2020
Site contact not available- reschedule and call for re-inspection.
|
||||
Miscellaneous/Other
Carried Forward
11/02/2020
Verify location and sizing of overcurrent protection of transformer secondary conductors.
|
||||
Electrical Final Inspection | Passed | 02/04/2021 | ||
Corrections:
Miscellaneous/Other
Resolved
02/04/2021
Verify location and sizing of overcurrent protection of transformer secondary conductors.
|
||||
Miscellaneous/Other
Comment Only
02/04/2021
Independent 3rd party evaluation attached.
|
||||
Miscellaneous/Other
Comment Only
02/04/2021
Independent 3rd party evaluation attached.
|