PREL202012908
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
04/01/2021
Separate inspection: Jones signs-
1. Installation of type CMR cable in return air ceilings. Repair or replace to code.
2. Installation of CMP type cable must be performed by MN State licensed TS or EA contractor- with permit and inspection.
3. Two signs are UL listed but the power supply lacks listing- field installed driver is required to be listed Class 2 and specifically permitted for sign use per the listing.
|
||||
Miscellaneous/Other
Outstanding
04/01/2021
04/01/2021-
Unlisted LED luminaires- not allowed.
|
||||
Electrical Final Inspection | Pending | |||
Electrical Rough-in Inspection | Partial Pass | 2/4/2021 | 10/30/2020 | |
Corrections:
Miscellaneous/Other
Comment Only
10/30/2020
2nd Floor wall RI OK- met contractor on site
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/24/2020 (12:30 - 2:30) | 11/24/2020 (PM) | 11/24/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/24/2020
Trench/UG inspections OK at multiple locations for floor boxes
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/1/2020 (8:00 - 10:00) | 12/1/2020 (AM) | 12/01/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/01/2020
Wall RI- OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/2/2020 (8:00 - 10:00) | 12/2/2020 (AM) | 12/02/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/02/2020
2nd floor- above ceiling RI at hard lid ceiling- progress inspection
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/3/2020 (8:00 - 10:00) | 12/3/2020 (AM) | 12/03/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/03/2020
Partial- progress inspection for RI for lighting/ above hard lid ceiling second floor
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/4/2020 (8:00 - 10:00) | 12/4/2020 (AM) | 12/04/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/04/2020
RI 2nd floor - progress inspection for above hard lid ceilings. Bathrooms and corridor OK.
|
||||
Electrical Rough-in Inspection | Not Ready | 12/7/2020 (8:00 - 10:00) | 12/7/2020 (AM) | 12/07/2020 |
Electrical Rough-in Inspection | Partial Pass | 12/8/2020 (8:00 - 10:00) | 12/8/2020 (AM) | 12/08/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/08/2020
Progress inspection OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/9/2020 (8:00 - 10:00) | 12/9/2020 (AM) | 12/09/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/09/2020
Remainder of hard lid ceiling on 2nd floor RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/10/2020 | 12/10/2020 (AM) | 12/10/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/10/2020
Progress inspection- 1st floor above hard lid at "horseshoe"- OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/11/2020 (8:00 - 10:00) | 12/11/2020 (AM) | 12/11/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/11/2020
site visit OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/15/2020 (10:00 - 12:00) | 12/15/2020 (AM) | 12/15/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/15/2020
Progress inspection - 1st floor hard lid RI OK for lighting
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/16/2020 (8:00 - 10:00) | 12/16/2020 (AM) | 12/16/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/16/2020
Progress inspection- above hard lid at first floor. Wall RI OK @ 3rd floor.
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/17/2020 (8:00 - 10:00) | 12/17/2020 (AM) | 12/17/2020 |
Electrical Rough-in Inspection | Not Ready | 12/18/2020 (8:00 - 10:00) | 12/18/2020 (AM) | 12/18/2020 |
Electrical Rough-in Inspection | Partial Pass | 12/22/2020 (8:00 - 10:00) | 12/22/2020 (AM) | 12/22/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/22/2020
Progress inspection ok- RI at TV walls- OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 01/13/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
01/13/2021
Progress inspection- back of house- office and conference room wall RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/19/2021 (2:30 - 3:30) | 1/19/2021 (PM) | 01/19/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/19/2021
Wall RI OK at first level back of house.
Wall RI OK at lower level storage
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/22/2021 (10:00 - 12:00) | 1/22/2021 (AM) | 01/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/22/2021
2nd floor - back of house above drop ceiling- OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/4/2021 (8:00 - 10:00) | 2/4/2021 (AM) | 02/04/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/04/2021
Questions at site- transformer installation
|
||||
Electrical Rough-in Inspection | Partial Pass | 02/25/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/25/2021
Above ceiling back of house 1st floor.- OK
Above ceiling at lower storage and conference room- OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/10/2021 (8:00 - 10:00) | 3/10/2021 (AM) | 03/10/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/10/2021
Partial final - OK at lower level storage area
|
||||
Electrical Rough-in Inspection | Failed | 3/19/2021 (12:30 - 2:30) | 3/19/2021 (PM) | 03/22/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
03/22/2021
1. Non plenum cables installed in a return air space.
|
||||
Miscellaneous/Other
Carried Forward
03/22/2021
2. Non listed- Class 1 type power supplies installed- improper sized wiring methods and cable sizing installed. Improper wiring in listed sign assembly based on power supply type. Note - the control apparatus for each sign had been mounted to the sign mounting bracket- this had been relocated to a 4 square J-box by the electrical contractor in an effort to mitigate the Class 1 power source.
|
||||
Miscellaneous/Other
Carried Forward
03/22/2021
3. #12 AWG MC cable not permitted on a 41 amp output DC power supply.
Note -supply is unlisted and considered a Class 1 power circuit.
|
||||
Miscellaneous/Other
Carried Forward
03/22/2021
At light tunnel: Unlisted Class 1 power supply.
Factory wiring methods are set up for limited energy installation only.
|
||||
Miscellaneous/Other
Carried Forward
03/22/2021
Provide all installation instructions.
Note: any replacement of drivers/power supplies must comply with: NEC 600. 24
Listed for use with signs and must be accompanied by the manufacturers installation instructions.
|
||||
Miscellaneous/Other
Carried Forward
03/22/2021
Call for re-inspection.
|
||||
Electrical Rough-in Inspection | Failed | 3/26/2021 (8:00 - 10:00) | 3/26/2021 (AM) | 03/26/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
03/26/2021
1. Non plenum cables installed in a return air space.
|
||||
Miscellaneous/Other
Carried Forward
03/26/2021
2. Non listed- Class 1 type power supplies installed- improper sized wiring methods and cable sizing installed. Improper wiring in listed sign assembly based on power supply type. Note - the control apparatus for each sign had been mounted to the sign mounting bracket- this had been relocated to a 4 square J-box by the electrical contractor in an effort to mitigate the Class 1 power source.
|
||||
Miscellaneous/Other
Carried Forward
03/26/2021
3. #12 AWG MC cable not permitted on a 41 amp output DC power supply.
Note -supply is unlisted and considered a Class 1 power circuit.
|
||||
Miscellaneous/Other
Carried Forward
03/26/2021
At light tunnel: Unlisted Class 1 power supply.
Factory wiring methods are set up for limited energy installation only.
|
||||
Miscellaneous/Other
Carried Forward
03/26/2021
Provide all installation instructions.
Note: any replacement of drivers/power supplies must comply with: NEC 600. 24
Listed for use with signs and must be accompanied by the manufacturers installation instructions.
|
||||
Miscellaneous/Other
Carried Forward
03/26/2021
Call for re-inspection.
|
||||
Miscellaneous/Other
Carried Forward
03/26/2021
Separate inspection: Jones signs-
1. Installation of type CMR cable in return air ceilings. Repair or replace to code.
2. Installation of CMP type cable must be performed by MN State licensed TS or EA contractor- with permit and inspection.
3. Two signs are UL listed but the power supply lacks listing- field installed driver is required to be listed Class 2 and specifically permitted for sign use per the listing.
|
||||
Electrical Rough-in Inspection | Failed | 04/01/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/01/2021
1. Non plenum cables installed in a return air space.
|
||||
Miscellaneous/Other
Comment Only
04/01/2021
2. Non listed- Class 1 type power supplies installed- improper sized wiring methods and cable sizing installed. Improper wiring in listed sign assembly based on power supply type. Note - the control apparatus for each sign had been mounted to the sign mounting bracket- this had been relocated to a 4 square J-box by the electrical contractor in an effort to mitigate the Class 1 power source.
|
||||
Miscellaneous/Other
Comment Only
04/01/2021
3. #12 AWG MC cable not permitted on a 41 amp output DC power supply.
Note -supply is unlisted and considered a Class 1 power circuit.
|
||||
Miscellaneous/Other
Comment Only
04/01/2021
At light tunnel: Unlisted Class 1 power supply.
Factory wiring methods are set up for limited energy installation only.
|
||||
Miscellaneous/Other
Comment Only
04/01/2021
Provide all installation instructions.
Note: any replacement of drivers/power supplies must comply with: NEC 600. 24
Listed for use with signs and must be accompanied by the manufacturers installation instructions.
|
||||
Miscellaneous/Other
Resolved
04/01/2021
Call for re-inspection.
|
||||
Miscellaneous/Other
Carried Forward
04/01/2021
Separate inspection: Jones signs-
1. Installation of type CMR cable in return air ceilings. Repair or replace to code.
2. Installation of CMP type cable must be performed by MN State licensed TS or EA contractor- with permit and inspection.
3. Two signs are UL listed but the power supply lacks listing- field installed driver is required to be listed Class 2 and specifically permitted for sign use per the listing.
|
||||
Miscellaneous/Other
Carried Forward
04/01/2021
04/01/2021-
Unlisted LED luminaires- not allowed.
|
||||
Electrical Final Inspection | Partial Pass | 4/8/2021 (12:30 - 2:30) | 4/8/2021 (PM) | 04/08/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/08/2021
Partial final- egress lighting OK.
Preliminary walk through OK.
Provide independent 3rd party evaluations for unlisted equipment and for listed assemblies that were field altered.
Complete all installations- call for final.
|
||||
Electrical Final Inspection | Not Ready | 4/9/2021 (12:30 - 2:30) | 4/9/2021 (PM) | 04/09/2021 |
Electrical Final Inspection | Passed | 4/16/2021 (12:30 - 2:30) | 4/16/2021 (PM) | 04/16/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/16/2021
Independent 3rd party evaluations received.
Final OK.
|