PREL202015221
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Passed | 8/20/2021 (10:00 - 12:00) | 8/20/2021 (AM) | 08/20/2021 |
| Electrical Final Inspection | Passed w/ Conditions | 8/20/2021 (10:00 - 12:00) | 8/20/2021 (AM) | 08/20/2021 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/20/2021
Proper labeling required for circuit in panel. Verify lock on device installed on CB and properly labeled with red.
|
||||