PREL202107558
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 7/30/2021 (8:00 - 10:00) | 7/30/2021 (AM) | 07/30/2021 |
Corrections:
Miscellaneous/Other
Comment Only
07/30/2021
Under ground by water main - ok
PVC stubbed through footing in same area- ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/15/2021 (10:00 - 12:00) | 11/15/2021 (AM) | 11/16/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/16/2021
Site visit OK.
UG / trench- partial- photos and on-site OK
2nd level slab for office area- OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/7/2021 (8:00 - 10:00) | 12/7/2021 (AM) | 12/07/2021 |
Underground Inspection | ||||
Corrections:
Miscellaneous/Other
Comment Only
12/07/2021
Progress inspection for UG - RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/10/2022 (8:00 - 10:00) | 1/10/2022 (AM) | 01/10/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/10/2022
First floor office walls - RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/31/2022 (8:00 - 10:00) | 1/31/2022 (AM) | 01/31/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/31/2022
Wall RI OK at north offices
|
||||
Miscellaneous/Other
Comment Only
01/31/2022
Preliminary review of service equipment
Verify GFPE testing
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/11/2022 (12:30 - 2:30) | 2/11/2022 (PM) | 02/11/2022 |
Corrections:
Miscellaneous/Other
Comment Only
02/11/2022
Bathrooms- RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/17/2022 (10:00 - 12:00) | 2/17/2022 (AM) | 02/17/2022 |
Corrections:
Miscellaneous/Other
Comment Only
02/17/2022
Above ceiling RI OK at upper level drop ceilings.
|
||||
Miscellaneous/Other
Carried Forward
02/17/2022
Shade control cabinet lacks an NRTL listing as an assembly.
The power supply is individually listed. The Listed power supply IS NOT Class 2.
There is a circuit board - that may limit the output power- no NRTL.
Wiring method installed requires listed Class 2 power supply.
NOT APPROVED
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/7/2022 (8:00 - 10:00) | 3/7/2022 (AM) | 03/07/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
03/07/2022
Shade control cabinet lacks an NRTL listing as an assembly.
The power supply is individually listed. The Listed power supply IS NOT Class 2.
There is a circuit board - that may limit the output power- no NRTL.
Wiring method installed requires listed Class 2 power supply.
NOT APPROVED
|
||||
Miscellaneous/Other
Comment Only
03/07/2022
Service OK to release to Xcel.
Install all required labeling, including available fault current.
|
||||
Miscellaneous/Other
Carried Forward
03/07/2022
Verify - equipment grounding sizing for future gen-set and transfer switch.
Size EGC on OCP device.
Based on 1600 AMP OCP- minimum EGC- 350 AL or 4/0 copper.
Verify pipe fill.
|
||||
Miscellaneous/Other
Carried Forward
03/07/2022
Verify available fault current at EM_ ( life-safety ) transfer switch.
See manufacturer chart- SCCR rating is specific to brand, size and frame type OCP protecting transfer switch.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/17/2022 (8:00 - 10:00) | 3/17/2022 (AM) | 03/17/2022 |
Corrections:
Miscellaneous/Other
Resolved
03/17/2022
Shade control cabinet lacks an NRTL listing as an assembly.
The power supply is individually listed. The Listed power supply IS NOT Class 2.
There is a circuit board - that may limit the output power- no NRTL.
Wiring method installed requires listed Class 2 power supply.
NOT APPROVED
|
||||
Miscellaneous/Other
Resolved
03/17/2022
Verify - equipment grounding sizing for future gen-set and transfer switch.
Size EGC on OCP device.
Based on 1600 AMP OCP- minimum EGC- 350 AL or 4/0 copper.
Verify pipe fill.
|
||||
Miscellaneous/Other
Resolved
03/17/2022
Verify available fault current at EM_ ( life-safety ) transfer switch.
See manufacturer chart- SCCR rating is specific to brand, size and frame type OCP protecting transfer switch.
|
||||
Miscellaneous/Other
Comment Only
03/17/2022
NE offices & labs ceiling RI
|
||||
Miscellaneous/Other
Carried Forward
03/17/2022
Improper working clearance at VAV boxes- sprinkler piping in front of power enclosure
|
||||
Miscellaneous/Other
Carried Forward
03/17/2022
Class 2 power cable introduced into power enclosure ( handy box ) at transfer fans.
See separate email.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/24/2022 (10:00 - 12:00) | 3/24/2022 (AM) | 03/24/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
03/24/2022
Improper working clearance at VAV boxes- sprinkler piping in front of power enclosure
|
||||
Miscellaneous/Other
Carried Forward
03/24/2022
Class 2 power cable introduced into power enclosure ( handy box ) at transfer fans.
See separate email.
|
||||
Miscellaneous/Other
Comment Only
03/24/2022
RTU -roof top inspection OK.
Label available fault current at units. All units reviewed today have a 65K SCCR
Call for inspection for small condensing unit and mini-splits when ready.
Verify/label available fault current at these units.
|
||||
Electrical Rough-in Inspection | Passed | 4/20/2022 (10:00 - 12:00) | 4/20/2022 (AM) | 04/20/2022 |
Corrections:
Miscellaneous/Other
Resolved
04/20/2022
Improper working clearance at VAV boxes- sprinkler piping in front of power enclosure
|
||||
Miscellaneous/Other
Resolved
04/20/2022
Class 2 power cable introduced into power enclosure ( handy box ) at transfer fans.
See separate email.
|
||||
Miscellaneous/Other
Comment Only
04/20/2022
Progress inspection OK.
Clearance issue above ceiling - correction OK.
Class 2 wiring at transfer fans- Correction -OK
|
||||
Electrical Final Inspection | Partial Pass | 5/26/2022 (8:00 - 10:00) | 5/26/2022 (AM) | 05/26/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
05/26/2022
Life Safety Generator start time required to be less than 10 sec., First test was 14 sec.
|
||||
Miscellaneous/Other
Carried Forward
05/26/2022
Panel covers missing in a couple electric rooms. These are in locked spaces.
|
||||
Miscellaneous/Other
Carried Forward
05/26/2022
50a feeds for dishwashers require GFCI protection from a listed class A device.
Current protection is not a listed device, only a listed component..
|
||||
Miscellaneous/Other
Carried Forward
05/26/2022
All furniture wiring required to be completed by a licensed electrical contractor. Talked with job sup to have furniture installers leave the work for electrical to complete. Contractor to go through work already completed and verify unlicensed work.
|
||||
Miscellaneous/Other
Comment Only
05/26/2022
Temporary OCC ok, if generator test passes building inspector, and Fire Marshall test.
|
||||
Electrical Final Inspection | Passed | 7/7/2022 (8:00 - 10:00) | 7/7/2022 (AM) | 07/08/2022 |
Corrections:
Miscellaneous/Other
Resolved
07/08/2022
Life Safety Generator start time required to be less than 10 sec., First test was 14 sec.
|
||||
Miscellaneous/Other
Resolved
07/08/2022
Panel covers missing in a couple electric rooms. These are in locked spaces.
|
||||
Miscellaneous/Other
Resolved
07/08/2022
50a feeds for dishwashers require GFCI protection from a listed class A device.
Current protection is not a listed device, only a listed component..
|
||||
Miscellaneous/Other
Resolved
07/08/2022
All furniture wiring required to be completed by a licensed electrical contractor. Talked with job sup to have furniture installers leave the work for electrical to complete. Contractor to go through work already completed and verify unlicensed work.
|
||||
Miscellaneous/Other
Comment Only
07/08/2022
Issues resolved, open items moved to new permit.
|