Permit Application Status

PREL202108354


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202108354
Electrical
Finaled
OXBOW REALTY PARTNERS LLC
Alteration/Repair/Replace
Install of Cable Tray and wiring into a 3000 amp service.
07/01/2021
07/14/2021
12/26/2023
06/29/2023

Locations

Permits

Permit Number: PREL202108354

Electrical
Finaled
07/14/2021
12/26/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 07/15/2021
Electrical Rough-in Inspection Partial Pass 7/29/2021 (10:00 - 12:00) 7/29/2021 (AM) 07/29/2021
Corrections:


Miscellaneous/Other
Comment Only
07/29/2021
Site meet and walk thru with project- ok

Electrical Rough-in Inspection Passed 08/13/2021
Electrical Final Inspection Partial Pass 10/6/2021 (8:00 - 10:00) 10/6/2021 (AM) 10/07/2021
Corrections:


Miscellaneous/Other
Comment Only
10/07/2021
Progress inspection OK. Verify system bonding jumper connection at zig zag transformer.

Electrical Final Inspection Partial Pass 10/13/2021 (8:00 - 10:00) 10/13/2021 (AM) 10/15/2021
Corrections:


Miscellaneous/Other
Comment Only
10/15/2021
Progress inspection.

Miscellaneous/Other
Outstanding
10/20/2021
Items for final approval: Submit as built cad riser- signed and stamped by Master of record. Label available fault current. Submit GFPE testing report for 3000 AMP distribution. Complete review for firestopping requirements between areas & rooms- fire stopping system requires City Building inspector review and site inspection for approvals.

Electrical Final Inspection Partial Pass 10/20/2021
Corrections:


Miscellaneous/Other
Carried Forward
10/20/2021
Items for final approval: Submit as built cad riser- signed and stamped by Master of record. Label available fault current. Submit GFPE testing report for 3000 AMP distribution. Complete review for firestopping requirements between areas & rooms- fire stopping system requires City Building inspector review and site inspection for approvals.

Electrical Rough-in Inspection Partial Pass 11/29/2021 (8:00 - 10:00) 11/29/2021 (AM) 12/03/2021
Corrections:


Miscellaneous/Other
Comment Only
12/03/2021
Progress inspections.

Electrical Rough-in Inspection Passed 04/26/2022
Electrical Final Inspection Passed 6/29/2023 (10:00 - 12:00) 6/29/2023 (AM) 06/29/2023
Corrections:


Miscellaneous/Other
Resolved
06/29/2023
Items for final approval: Submit as built cad riser- signed and stamped by Master of record. Label available fault current. Submit GFPE testing report for 3000 AMP distribution. Complete review for firestopping requirements between areas & rooms- fire stopping system requires City Building inspector review and site inspection for approvals.