PREL202108897
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Partial Pass | 7/27/2021 (8:00 - 10:00) | 7/27/2021 (AM) | 07/27/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/27/2021
Wall RI- ok
|
||||
| Electrical Rough-in Inspection | Passed | 9/15/2021 (8:00 - 10:00) | 9/15/2021 (AM) | 09/15/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/15/2021
Above drop ceiling RI OK
|
||||
| Electrical Final Inspection | Passed | 10/20/2021 (8:00 - 10:00) | 10/20/2021 (AM) | 10/20/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/20/2021
Final Ok- walk through with contractor.
Verbal all egress lighting both exit & emergency - new or existing must be fully functioning.
Repair or replace existing to code. - verify location requirements with city building inspector.
|
||||