PREL202109808
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Not Ready | 8/25/2021 (8:00 - 10:00) | 8/25/2021 (AM) | 08/25/2021 |
Electrical Final Inspection | Failed | 9/14/2021 (8:00 - 10:00) | 9/14/2021 (AM) | 09/14/2021 |
Corrections:
Miscellaneous/Other
Comment Only
09/14/2021
No RI inspections.
Site meeting- on 09/09/2021- with contractor, owner rep and electrical engineer.
Based on this walk through it was noted that:
No GEC connection to transformer.
No arc flash warning labels.
Equipment requires documentation and labeling of the available fault current.
Improperly located seal-off.
Notation of fan equipment not listed for classified locations.
Agreement made of the permanent marking of the Class 1 Division 2 boundary
@ cement slab areas.
Unlisted industrial cabinet requires independent 3rd party evaluation.
Electrical Engineer is to make revisions to construction documents based on site meeting.
No formal inspection was requested or performed at this meeting.
|
||||
Miscellaneous/Other
Carried Forward
09/14/2021
Based on inspection 09/14/2021.
1. Improper tap conductor sizing.
2. No labeling of available fault current.
3. No arc flash warning labels installed.
Cement slab has not had Division 2 Boundary permanently identified.
|
||||
Miscellaneous/Other
Comment Only
09/14/2021
Corrections OK for:
Grounding of separately derived system.
Independent 3rd party evaluation received/accepted.
Seal off relocated- OK pending final documentation of Class and Division boundary.
|
||||
Electrical Final Inspection | Partial Pass | 10/20/2021 | ||
Corrections:
Miscellaneous/Other
Resolved
10/20/2021
Based on inspection 09/14/2021.
1. Improper tap conductor sizing.
2. No labeling of available fault current.
3. No arc flash warning labels installed.
Cement slab has not had Division 2 Boundary permanently identified.
|
||||
Miscellaneous/Other
Comment Only
10/20/2021
Corrections OK for arc flash warning labels and for sizing of tap conductors- tap conductors changed out to full size 3/0 copper- no longer considered a "tap."
|
||||
Miscellaneous/Other
Outstanding
10/20/2021
Panelboards & industrial control panel requires labeling of the available fault current.
Per electrical engineer design- concrete slab to be painted/marked as to Class 1 Division boundaries. Cement slab has not had Division 2 Boundary permanently identified.
|
||||
Electrical Final Inspection | Passed | 6/27/2023 (12:30 - 2:30) | 6/27/2023 (PM) | 06/27/2023 |
Corrections:
Miscellaneous/Other
Resolved
06/27/2023
Panelboards & industrial control panel requires labeling of the available fault current.
Per electrical engineer design- concrete slab to be painted/marked as to Class 1 Division boundaries. Cement slab has not had Division 2 Boundary permanently identified.
|