PREL202110056
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Final Inspection | Pending | |||
Electrical Rough-in Inspection | Partial Pass | 12/1/2021 (8:00 - 10:00) | 12/1/2021 (AM) | 12/01/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/01/2021
Underground ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/21/2022 (8:00 - 10:00) | 3/21/2022 (AM) | 03/21/2022 |
Corrections:
Miscellaneous/Other
Comment Only
03/21/2022
Review of workspace clearance isssues
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/20/2022 (12:30 - 2:30) | 12/20/2022 (PM) | 12/22/2022 |
Corrections:
Miscellaneous/Other
Comment Only
12/22/2022
Switch gear line up, ok
Need to verify if unfused disconnect switch is allowed on utility side of services. Provide engineering documentation for reasoning and code compliance.
|
||||
Miscellaneous/Other
Carried Forward
12/22/2022
Move 13.8Kv line from unfused areas of line up to feed transformer on opposite end.
|
||||
Electrical Rough-in Inspection | Passed | 12/27/2022 (8:00 - 3:30) | 12/27/2022 (AM) | 12/27/2022 |
Corrections:
Miscellaneous/Other
Outstanding
12/22/2022
Move 13.8Kv line from unfused areas of line up to feed transformer on opposite end.
|
||||
Miscellaneous/Other
Outstanding
12/27/2022
Service ok
|