Permit Application Status

PREL202110717


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202110717
Electrical
Finaled
DARK HORSE HOSPITALITY LLC
Other
New Building Electrical Work
08/13/2021
09/17/2021
03/26/2024
09/28/2023

Locations

Permits

Permit Number: PREL202110717

Electrical
Finaled
09/17/2021
03/26/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 9/21/2021 (PM) 09/21/2021
Site Visit only
Corrections:


Miscellaneous/Other
Comment Only
09/21/2021
Site visit only

Electrical Rough-in Inspection Partial Pass 10/13/2021 (8:00 - 10:00) 10/13/2021 (AM) 10/13/2021
Corrections:


Miscellaneous/Other
Comment Only
10/13/2021
Site visit/questions at site. Progress inspection OK

Electrical Rough-in Inspection Partial Pass 11/9/2021 (12:30 - 2:30) 11/9/2021 (PM) 11/09/2021
Corrections:


Miscellaneous/Other
Comment Only
11/09/2021
Visual Ok for UG- Verify final grade height prior to final inspection approval

Electrical Rough-in Inspection Passed w/ Conditions 11/24/2021 (2:30 - 3:30) 11/24/2021 (PM) 11/29/2021
Corrections:


Miscellaneous/Other
Outstanding
11/29/2021
Temporary service for construction. OK to release to Xcel- verify and label available fault current at service.

Electrical Rough-in Inspection Partial Pass 12/15/2021 (10:00 - 12:00) 12/15/2021 (AM) 12/15/2021
Corrections:


Miscellaneous/Other
Comment Only
12/15/2021
Partial pass- North area corridor and units. RI OK Note: units do not have panelboards installed and the limited energy for fire alarm notification is yet completed. Call for -additional inspections when the work is completed prior to covering

Electrical Rough-in Inspection Partial Pass 1/4/2022 (10:00 - 12:00) 1/4/2022 (AM) 01/04/2022
Corrections:


Miscellaneous/Other
Comment Only
01/04/2022
4th floor RI complete, units, corridor, common areas, stair

Electrical Rough-in Inspection Partial Pass 1/18/2022 (8:00 - 10:00) 1/18/2022 (AM) 01/18/2022
Corrections:


Miscellaneous/Other
Comment Only
01/18/2022
Progress inspection of units 3rd floor units as signed off - RI OK

Electrical Rough-in Inspection Partial Pass 1/20/2022 (10:00 - 12:00) 1/20/2022 (AM) 01/20/2022
Corrections:


Miscellaneous/Other
Comment Only
01/20/2022
3rd floor RI OK- units & corridor

Electrical Rough-in Inspection Partial Pass 2/9/2022 (8:00 - 10:00) 2/9/2022 (AM) 02/09/2022
Corrections:


Miscellaneous/Other
Comment Only
02/09/2022
2nd floor units- RI OK - see door frames for signoff. 10 units remain to inspect on 2nd floor.

Electrical Rough-in Inspection Partial Pass 2/28/2022 (8:00 - 10:00) 2/28/2022 (AM) 02/28/2022
Corrections:


Miscellaneous/Other
Carried Forward
02/28/2022
4th floor hard lid ceiling ri

Electrical Rough-in Inspection Partial Pass 3/15/2022 (8:00 - 10:00) 3/15/2022 (AM) 03/15/2022
Corrections:


Miscellaneous/Other
Comment Only
03/15/2022
4th floor hard lid ceiling ri

Miscellaneous/Other
Comment Only
03/15/2022
4th floor soffit RI OK at corridor

Electrical Rough-in Inspection Partial Pass 3/28/2022 (8:00 - 10:00) 3/28/2022 (AM) 03/29/2022
Corrections:


Miscellaneous/Other
Comment Only
03/29/2022
1st floor units- RI OK as marked at door frames on site.

Electrical Rough-in Inspection Partial Pass 4/6/2022 (8:00 - 10:00) 4/6/2022 (AM) 04/06/2022
Corrections:


Miscellaneous/Other
Comment Only
04/06/2022
1st floor units RI OK- all except room with homeruns passing through. 3rd floor soffits OK at stairs going north - RI OK except bathrooms not ready yet

Electrical Rough-in Inspection Partial Pass 5/12/2022 (8:00 - 10:00) 5/12/2022 (AM) 05/12/2022
Corrections:


Miscellaneous/Other
Comment Only
05/12/2022
4th floor bath walls - ok 2 & 3 soffits- ok 3rd floor hallway- ok

Electrical Rough-in Inspection Partial Pass 5/23/2022 (Morning) 5/23/2022 (AM) 05/23/2022
Corrections:


Miscellaneous/Other
Comment Only
05/23/2022
2nd floor hallway. 1st level unit with HR installed- ok

Electrical Rough-in Inspection Partial Pass 5/31/2022 (12:30 - 2:30) 5/31/2022 (PM) 05/31/2022
Corrections:


Miscellaneous/Other
Comment Only
05/31/2022
4th floor bath ceilings- ok

Electrical Rough-in Inspection Partial Pass 6/3/2022 (2:30 - 3:30) 6/3/2022 (PM) 06/03/2022
Corrections:


Miscellaneous/Other
Comment Only
06/03/2022
Bathroom ceilings. 3rd floor - ok

Electrical Rough-in Inspection Partial Pass 7/6/2022 (10:00 - 12:00) 7/6/2022 (AM) 07/06/2022
Corrections:


Miscellaneous/Other
Comment Only
07/06/2022
bathroom ceilings throughout 4th, 3rd, and 2nd- ok

Electrical Rough-in Inspection Partial Pass 7/13/2022 (10:00 - 12:00) 7/13/2022 (AM) 07/13/2022
Corrections:


Miscellaneous/Other
Comment Only
07/13/2022
2nd and partial 1st floor room ceilings.

Electrical Rough-in Inspection Partial Pass 7/28/2022 (12:30 - 2:30) 7/28/2022 (PM) 07/28/2022
Corrections:


Miscellaneous/Other
Comment Only
07/28/2022
1st floor unit ceilings. Partial wall RI in common areas.

Electrical Rough-in Inspection Partial Pass 7/29/2022 (8:00 - 10:00) 7/29/2022 (AM) 07/29/2022
Corrections:


Miscellaneous/Other
Comment Only
07/29/2022
Partial pool bonding for rebar in pool no deck bonding installed.

Electrical Rough-in Inspection Partial Pass 8/24/2022 (8:00 - 10:00) 8/24/2022 (AM) 08/25/2022
Corrections:


Miscellaneous/Other
Comment Only
08/25/2022
RI for lighting in canopy area. - ok

Electrical Rough-in Inspection Passed 9/9/2022 (10:00 - 12:00) 9/9/2022 (AM) 09/09/2022
Corrections:


Miscellaneous/Other
Comment Only
09/09/2022
Bathroom ceilings 1st level - ok Partial hallway on 1st level- ok

Electrical Rough-in Inspection Passed w/ Conditions 9/22/2022 (2:30 - 3:30) 9/22/2022 (PM) 09/22/2022
Corrections:


Miscellaneous/Other
Comment Only
09/22/2022
1st floor hallway-ok Temp wiring, shall be removed or lowered below the ceiling to allow for removal when permanent power is connected.

Electrical Rough-in Inspection Partial Pass 10/5/2022 (12:30 - 2:30) 10/5/2022 (PM) 10/06/2022
Corrections:


Miscellaneous/Other
Comment Only
10/06/2022
Pool deck bonding- OK

Electrical Rough-in Inspection Partial Pass 11/14/2022 (10:00 - 12:00) 11/14/2022 (AM) 11/14/2022
Corrections:


Miscellaneous/Other
Comment Only
11/14/2022
Above ceilings in lobby area. Elevator area. - ok

Electrical Rough-in Inspection Partial Pass 12/6/2022 (12:30 - 2:30) 12/6/2022 (PM) 12/06/2022
Corrections:


Miscellaneous/Other
Comment Only
12/06/2022
Elevator Lobby area ceilings - ok

Electrical Rough-in Inspection Partial Pass 12/14/2022 (10:00 - 12:00) 12/14/2022 (AM) 12/14/2022
Corrections:


Miscellaneous/Other
Comment Only
12/14/2022
Above ceiling in kitchen storage area- ok

Electrical Rough-in Inspection Failed 1/9/2023 (12:30 - 2:30) 1/9/2023 (PM) 01/10/2023
Corrections:


Miscellaneous/Other
Carried Forward
01/10/2023
Service wiring, not properly sized for service. Derating only allows for a 3000a service. Conductors must be sized to OCP device over 800a.

Miscellaneous/Other
Carried Forward
01/10/2023
Bonding jumper in CT needs to be sized to total conductor sizing (12.5%).

Electrical Rough-in Inspection Partial Pass 1/13/2023 (10:00 - 12:00) 1/13/2023 (AM) 01/13/2023
Corrections:


Miscellaneous/Other
Carried Forward
01/13/2023
Service wiring, not properly sized for service. Derating only allows for a 3000a service. Conductors must be sized to OCP device over 800a.

Miscellaneous/Other
Carried Forward
01/13/2023
Bonding jumper in CT needs to be sized to total conductor sizing (12.5%).

Miscellaneous/Other
Comment Only
01/13/2023
Ceilings in lobby and partial basement walls - ok

Electrical Rough-in Inspection Partial Pass 1/24/2023 (12:30 - 2:30) 1/24/2023 (PM) 01/24/2023
Corrections:


Miscellaneous/Other
Resolved
01/24/2023
Service wiring, not properly sized for service. Derating only allows for a 3000a service. Conductors must be sized to OCP device over 800a.

Miscellaneous/Other
Resolved
01/24/2023
Bonding jumper in CT needs to be sized to total conductor sizing (12.5%).

Miscellaneous/Other
Comment Only
01/24/2023
Service wiring corrected - ok Xcel contacted for connection

Electrical Rough-in Inspection Partial Pass 1/31/2023 (8:00 - 10:00) 1/31/2023 (AM) 02/01/2023
Corrections:


Miscellaneous/Other
Comment Only
02/01/2023
Pool lights required minimum height of 7’6”. Bonding for exposed metal parts of all fixtures.

Electrical Rough-in Inspection Partial Pass 2/3/2023 (8:00 - 10:00) 2/3/2023 (AM) 02/03/2023
Corrections:


Miscellaneous/Other
Comment Only
02/03/2023
Pool area bonding - ok

Electrical Rough-in Inspection Partial Pass 2/24/2023 (10:00 - 12:00) 2/24/2023 (AM) 02/24/2023
Corrections:


Miscellaneous/Other
Comment Only
02/24/2023
3 basement ceiling areas- ok

Electrical Rough-in Inspection Failed 2/28/2023 (10:00 - 12:00) 2/28/2023 (AM) 02/28/2023
Corrections:


Miscellaneous/Other
Carried Forward
02/28/2023
Furniture feed receptacles being used in place of permanent wiring in bar area.

Electrical Rough-in Inspection Partial Pass 3/8/2023 (8:00 - 10:00) 3/8/2023 (AM) 03/08/2023
Corrections:


Miscellaneous/Other
Carried Forward
03/08/2023
Furniture feed receptacles being used in place of permanent wiring in bar area.

Miscellaneous/Other
Comment Only
03/08/2023
Above ceiling in vestibule area- ok

Electrical Rough-in Inspection Partial Pass 3/29/2023 (12:30 - 2:30) 3/29/2023 (PM) 03/30/2023
Corrections:


Miscellaneous/Other
Outstanding
03/08/2023
Furniture feed receptacles being used in place of permanent wiring in bar area.

Miscellaneous/Other
Comment Only
03/30/2023
Site visit walk through. Pool area

Electrical Rough-in Inspection Partial Pass 3/31/2023 (10:00 - 12:00) 3/31/2023 (AM) 03/31/2023
Corrections:


Miscellaneous/Other
Comment Only
03/31/2023
Site meet

Electrical Rough-in Inspection Passed 4/5/2023 (8:00 - 10:00) 4/5/2023 (AM) 04/05/2023
Corrections:


Miscellaneous/Other
Comment Only
04/05/2023
RI complete. Finals for first half of 4th floor.

Electrical Final Inspection Partial Pass 4/7/2023 (12:30 - 2:30) 4/7/2023 (PM) 04/08/2023
Corrections:


Miscellaneous/Other
Comment Only
04/08/2023
Partial room finals 4th floor.

Electrical Rough-in Inspection Passed 4/17/2023 (12:30 - 2:30) 4/17/2023 (PM) 04/17/2023
basement rough-in
Corrections:


Miscellaneous/Other
Comment Only
04/17/2023
Above ceiling in basement area 3 rooms and hallway. Niche light sealant for grounding lug- ok Finals for 10 rooms on 4h floor.

Electrical Final Inspection Partial Pass 4/20/2023 (8:00 - 10:00) 4/20/2023 (AM) 04/20/2023
Corrections:


Miscellaneous/Other
Comment Only
04/20/2023
Partial finals for 3rd floor.

Electrical Final Inspection Partial Pass 4/21/2023 (8:00 - 10:00) 4/21/2023 (AM) 04/21/2023
Corrections:


Miscellaneous/Other
Comment Only
04/21/2023
3rd floor finals area B

Electrical Final Inspection Partial Pass 4/25/2023 (12:30 - 2:30) 4/25/2023 (PM) 04/25/2023
Corrections:


Miscellaneous/Other
Comment Only
04/25/2023
3rd floor unit finals

Electrical Final Inspection Partial Pass 4/26/2023 (12:30 - 2:30) 4/26/2023 (PM) 04/26/2023
Corrections:


Miscellaneous/Other
Comment Only
04/26/2023
Common area space 4th and 3rd

Miscellaneous/Other
Outstanding
04/26/2023
Laundry areas require GFCI’s 210.8B

Electrical Final Inspection Partial Pass 4/27/2023 (8:00 - 10:00) 4/27/2023 (AM) 04/27/2023
Corrections:


Miscellaneous/Other
Comment Only
04/27/2023
Unit finals 2nd floor.

Electrical Final Inspection Partial Pass 5/1/2023 (10:00 - 12:00) 5/1/2023 (AM) 05/01/2023
Corrections:


Miscellaneous/Other
Comment Only
05/01/2023
Partial finals 2nd floor

Electrical Final Inspection Partial Pass 5/2/2023 (10:00 - 12:00) 5/2/2023 (AM) 05/02/2023
Corrections:


Miscellaneous/Other
Comment Only
05/02/2023
2 nd floor unit finals

Electrical Final Inspection Passed 5/3/2023 (12:30 - 2:30) 5/3/2023 (PM) 05/03/2023
Corrections:


Miscellaneous/Other
Comment Only
05/03/2023
Bar RI

Electrical Final Inspection Partial Pass 5/10/2023 (8:00 - 10:00) 5/10/2023 (AM) 05/10/2023
Corrections:


Miscellaneous/Other
Comment Only
05/10/2023
Unit finals for corner units 2-4.

Electrical Final Inspection Partial Pass 5/12/2023 (8:00 - 10:00) 5/12/2023 (AM) 05/12/2023
Corrections:


Miscellaneous/Other
Comment Only
05/12/2023
Above ceiling no in kitchen 2,3,&4 corner units - ok

Electrical Final Inspection Partial Pass 5/23/2023 (10:00 - 12:00) 5/23/2023 (AM) 05/23/2023
Corrections:


Miscellaneous/Other
Comment Only
05/23/2023
Unit finals 1st floor

Electrical Final Inspection Partial Pass 5/24/2023 (10:00 - 12:00) 5/24/2023 (AM) 05/24/2023
Corrections:


Miscellaneous/Other
Comment Only
05/24/2023
Unit finals 1st floor middle area.

Electrical Final Inspection Partial Pass 5/26/2023 (10:00 - 12:00) 5/26/2023 (AM) 05/27/2023
Corrections:


Miscellaneous/Other
Comment Only
05/27/2023
Unit finals 1st floor south. Office area finals.

Electrical Final Inspection Partial Pass 5/30/2023 (8:00 - 10:00) 5/30/2023 (AM) 05/30/2023
Corrections:


Miscellaneous/Other
Outstanding
05/30/2023
Kitchen partial final, Bar area final. Available fault current to high for branch breakers in kitchen area.

Electrical Final Inspection Partial Pass 5/31/2023 (12:30 - 2:30) 5/31/2023 (PM) 05/31/2023
Corrections:


Miscellaneous/Other
Comment Only
05/31/2023
Partial basement walk through. Discuss series rating for fault currents.

Electrical Final Inspection Partial Pass 6/1/2023 (8:00 - 10:00) 6/1/2023 (AM) 06/01/2023
Corrections:


Miscellaneous/Other
Comment Only
06/01/2023
Walk through on roof.

Electrical Final Inspection Failed 6/2/2023 (8:00 - 10:00) 6/2/2023 (AM) 06/02/2023
Corrections:


Miscellaneous/Other
Carried Forward
06/02/2023
Egress door required on service room.

Miscellaneous/Other
Carried Forward
06/02/2023
Adjust pool bonding as discussed.

Miscellaneous/Other
Carried Forward
06/02/2023
Pool light shall be properly seated and sealed to forming shell. Per 680.23(5)

Electrical Final Inspection Partial Pass 6/6/2023 (12:30 - 2:30) 6/6/2023 (PM) 06/06/2023
Corrections:


Miscellaneous/Other
Carried Forward
07/06/2023
Egress door required on service room.

Miscellaneous/Other
Resolved
06/06/2023
Adjust pool bonding as discussed.

Miscellaneous/Other
Carried Forward
07/06/2023
Pool light shall be properly seated and sealed to forming shell. Per 680.23(5)

Miscellaneous/Other
Carried Forward
07/06/2023
Outdoor disconnect grounding.

Miscellaneous/Other
Carried Forward
07/06/2023
Outline lighting driver listing and labeling.

Lighting Inspection Passed 6/29/2023 (2:30 - 3:30) 7/17/2023 (AM) 06/29/2023
Electrical Final Inspection Failed 7/6/2023 (12:30 - 2:30) 7/6/2023 (PM) 07/06/2023
Corrections:


Miscellaneous/Other
Outstanding
07/06/2023
150w driver for tape light not class 2

Miscellaneous/Other
Outstanding
07/06/2023
Panic hardware still needs to be installed for service room.

Miscellaneous/Other
Outstanding
07/06/2023
Clean debris and garbage out of electric rooms.

Electrical Final Inspection Passed 9/27/2023 (12:30 - 2:30) 9/27/2023 (PM) 09/28/2023
Corrections:


Miscellaneous/Other
Resolved
09/27/2023
Egress door required on service room.

Miscellaneous/Other
Resolved
09/27/2023
Pool light shall be properly seated and sealed to forming shell. Per 680.23(5)

Miscellaneous/Other
Resolved
09/27/2023
Outdoor disconnect grounding.

Miscellaneous/Other
Resolved
09/27/2023
Outline lighting driver listing and labeling.