Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 10/12/2021 (10:00 - 12:00) | 10/12/2021 (AM) | 10/12/2021 |
Corrections:
Miscellaneous/Other
Comment Only
10/12/2021
Wall RI- ok
Stat and FA permits required for electrical work before above ceiling work.
|
||||
Electrical Rough-in Inspection | Passed | 10/21/2021 (2:30 - 3:30) | 10/21/2021 (PM) | 10/21/2021 |
Corrections:
Miscellaneous/Other
Comment Only
10/21/2021
Above ceilings- ok
|
||||
Electrical Final Inspection | Partial Pass | 11/8/2021 (12:30 - 2:30) | 11/8/2021 (PM) | 11/08/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/08/2021
Phase l final
Contact Chad 763-226-1360
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/29/2021 (12:30 - 2:30) | 11/29/2021 (PM) | 11/29/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/29/2021
Phase 2 wall RI- ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/9/2021 (10:00 - 12:00) | 12/9/2021 (AM) | 12/09/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/09/2021
Above ceilings ok for small office areas.
|
||||
Electrical Final Inspection | Passed | 1/7/2022 (10:00 - 12:00) | 1/7/2022 (AM) | 01/07/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/07/2022
Final- ok
|