PREL202113342
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Final Inspection | Pending | |||
Electrical Rough-in Inspection | Partial Pass | 10/15/2021 | ||
Electrical Rough-in Inspection | Partial Pass | 10/15/2021 | ||
Electrical Rough-in Inspection | Passed | 11/17/2021 (10:00 - 12:00) | 11/17/2021 (AM) | 11/17/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/17/2021
Above ceiling
|
||||
Electrical Final Inspection | Partial Pass | 11/17/2021 (10:00 - 12:00) | 11/17/2021 (AM) | 11/17/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/17/2021
Final Ok contingent on available fault current ratings of new panelboards.
Partial pass- Ok to open.
|