PREL202115868
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 12/21/2021 (8:00 - 10:00) | 12/21/2021 (AM) | 12/21/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/21/2021
Wall RI OK- suite #410
|
||||
Electrical Rough-in Inspection | Passed | 1/10/2022 (8:00 - 10:00) | 1/10/2022 (AM) | 01/10/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/10/2022
Above ceiling Ok for power & lighting- RI OK
|
||||
Electrical Final Inspection | Partial Pass | 2/3/2022 (10:00 - 12:00) | 2/3/2022 (AM) | 02/03/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
02/03/2022
Left note for general contractor- in regards to fire alarm cable work and temperature control wiring- no calls for inspection and not covered under this permit.
|
||||
Miscellaneous/Other
Carried Forward
02/03/2022
Partial pass for power & lighting.
Wired partition furniture to be installed- not installed yet.
|
||||
Electrical Final Inspection | Passed | 2/16/2022 (12:30 - 2:30) | 2/16/2022 (PM) | 02/16/2022 |
Corrections:
Miscellaneous/Other
Comment Only
02/16/2022
Left note for general contractor- in regards to fire alarm cable work and temperature control wiring- no calls for inspection and not covered under this permit.
|
||||
Miscellaneous/Other
Resolved
02/16/2022
Partial pass for power & lighting.
Wired partition furniture to be installed- not installed yet.
|
||||
Miscellaneous/Other
Comment Only
02/16/2022
Final OK for power & lighting
|