PREL202116178
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Partial Pass | 7/13/2022 (8:00 - 10:00) | 7/13/2022 (AM) | 07/13/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/13/2022
Site meet only
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/22/2022 (12:30 - 2:30) | 9/22/2022 (PM) | 09/22/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/22/2022
6th floor wall RI first 11 rooms - ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/29/2022 (12:30 - 2:30) | 9/29/2022 (PM) | 09/29/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/29/2022
5th floor 11 room RI- ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/6/2022 (12:30 - 2:30) | 10/6/2022 (PM) | 10/06/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/06/2022
11 room RI on 3rd floor - ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/13/2022 (12:30 - 2:30) | 10/13/2022 (PM) | 10/13/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/13/2022
Third floor unit RI’s
First floor model unit - ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/19/2022 (12:30 - 2:30) | 10/19/2022 (PM) | 10/19/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/19/2022
UG for service pipes- ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/26/2022 (12:30 - 2:30) | 10/26/2022 (PM) | 10/26/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/26/2022
2nd floor partial RI- ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 11/8/2022 (2:30 - 3:30) | 11/8/2022 (PM) | 11/09/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/09/2022
UG work for parking lot area and drive lanes - OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 11/10/2022 (8:00 - 10:00) | 11/10/2022 (AM) | 11/10/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/10/2022
Partial Above ceiling on 6th floor.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 11/17/2022 (2:30 - 3:30) | 11/17/2022 (PM) | 11/17/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/17/2022
6th floor RI phase 2- ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 11/23/2022 (2:30 - 3:30) | 11/23/2022 (PM) | 11/23/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/23/2022
Partial 5th floor RI
|
||||
| Electrical Rough-in Inspection | Partial Pass | 12/1/2022 (10:00 - 12:00) | 12/1/2022 (AM) | 12/01/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/01/2022
RI for 3 rooms on 5th, common areas, and stairs
|
||||
| Electrical Rough-in Inspection | Partial Pass | 12/8/2022 (2:30 - 3:30) | 12/8/2022 (PM) | 12/08/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/08/2022
4 th floor RI- ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 12/15/2022 (12:30 - 2:30) | 12/15/2022 (PM) | 12/20/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/20/2022
RI for 4th floor - ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 12/22/2022 (Morning) | 12/22/2022 (AM) | 12/22/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/22/2022
Partial 2nd floor RI- ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 12/29/2022 (12:30 - 2:30) | 12/29/2022 (PM) | 12/29/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/29/2022
6 floor ceilings and units on 2nd- ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 1/26/2023 (10:00 - 12:00) | 1/26/2023 (AM) | 01/30/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/30/2023
Partial RI for 1st floor
|
||||
| Electrical Rough-in Inspection | Partial Pass | 2/2/2023 (12:30 - 2:30) | 2/2/2023 (PM) | 02/02/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/02/2023
1st floor RI partial rooms- ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 2/7/2023 (2:30 - 3:30) | 2/7/2023 (PM) | 02/08/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/08/2023
2nd floor hallway.- ok
2 units on 1st- ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 2/24/2023 (12:30 - 2:30) | 2/24/2023 (PM) | 02/24/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/24/2023
5 units on 1st floor north end- ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 3/2/2023 (10:00 - 12:00) | 3/2/2023 (AM) | 03/02/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/02/2023
Partial service metering banks only.
Xcel contacted
|
||||
| Electrical Rough-in Inspection | Partial Pass | 3/9/2023 (10:00 - 12:00) | 3/9/2023 (AM) | 03/09/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/09/2023
Service connections require bonding and GEC connection.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 3/10/2023 (12:30 - 2:30) | 3/10/2023 (PM) | 03/11/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/11/2023
New service install-ok for release to Xcel ( contacted for connection).
Still need bonding inspections to water service and other equipment install.
|
||||
| Electrical Rough-in Inspection | Passed | 3/16/2023 (12:30 - 2:30) | 3/16/2023 (PM) | 03/16/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/16/2023
Common area RI- ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 4/7/2023 (12:30 - 2:30) | 4/7/2023 (PM) | 04/08/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/08/2023
Ceiling RI at exterior glass areas- ok
Damaged MC in north soffit area needs to be replaced.
|
||||
| Electrical Final Inspection | Partial Pass | 4/12/2023 (8:00 - 10:00) | 4/12/2023 (AM) | 04/12/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/12/2023
Finals for 1st phase.
Islands require receptacle per sq. Ft. Measurements.
|
||||
| Electrical Final Inspection | Partial Pass | 4/13/2023 (10:00 - 12:00) | 4/13/2023 (AM) | 04/14/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/14/2023
Unit Ri for 5th floor- ok
|
||||
| Electrical Final Inspection | Partial Pass | 4/19/2023 (12:30 - 2:30) | 4/19/2023 (PM) | 04/19/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/19/2023
4th floor finals- ok
|
||||
| Electrical Rough-in Inspection | Passed | 4/21/2023 (10:00 - 12:00) | 4/21/2023 (AM) | 04/21/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/21/2023
1st floor hallway ceiling and pet wash room.
|
||||
| Electrical Final Inspection | Partial Pass | 4/27/2023 (12:30 - 2:30) | 4/27/2023 (PM) | 04/27/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/27/2023
Unit finals 3rd floor.
Elevator lobbys RI
|
||||
| Electrical Rough-in Inspection | Partial Pass | 5/2/2023 (12:30 - 2:30) | 5/2/2023 (PM) | 05/02/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/02/2023
Ceiling RI stairwell and elevator lobby’s.
|
||||
| Electrical Final Inspection | Partial Pass | 5/16/2023 (12:30 - 2:30) | 5/16/2023 (PM) | 05/16/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/16/2023
6th floor area B finals
|
||||
| Electrical Final Inspection | Partial Pass | 5/23/2023 (12:30 - 2:30) | 5/23/2023 (PM) | 05/23/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/23/2023
5th floor area B finals
|
||||
| Electrical Final Inspection | Partial Pass | 5/24/2023 (12:30 - 2:30) | 5/24/2023 (PM) | 05/24/2023 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/25/2023
GFCI required for receptacles within 6’ of vanities.
|
||||
|
Miscellaneous/Other
Carried Forward
05/25/2023
Partial pass on units without decks.
|
||||
| Electrical Final Inspection | Partial Pass | 5/25/2023 (12:30 - 2:30) | 5/25/2023 (PM) | 05/25/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/25/2023
Unit finals 3rd floor
|
||||
| Electrical Final Inspection | Partial Pass | 5/30/2023 (12:30 - 2:30) | 5/30/2023 (PM) | 05/30/2023 |
|
Corrections:
Miscellaneous/Other
Resolved
05/30/2023
GFCI required for receptacles within 6’ of vanities.
|
||||
|
Miscellaneous/Other
Outstanding
05/25/2023
Partial pass on units without decks.
|
||||
|
Miscellaneous/Other
Comment Only
05/30/2023
2nd floor unit finals area B
|
||||
| Electrical Final Inspection | Not Ready | 6/1/2023 (12:30 - 2:30) | 6/1/2023 (PM) | 06/01/2023 |
| Electrical Final Inspection | Not Ready | 6/2/2023 (12:30 - 2:30) | 6/2/2023 (PM) | 06/02/2023 |
| Electrical Final Inspection | Partial Pass | 6/12/2023 (12:30 - 2:30) | 6/12/2023 (PM) | 06/12/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/12/2023
Hallway and common space 6-2
|
||||
| Electrical Final Inspection | Partial Pass | 6/21/2023 (10:00 - 12:00) | 6/21/2023 (AM) | 06/21/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/21/2023
Partial Finals on 1st floor units.
DW receptacle finish installing.
Find fault in LR circuit tripping CB.
|
||||
| Electrical Final Inspection | Partial Pass | 6/22/2023 (10:00 - 12:00) | 6/22/2023 (AM) | 06/22/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/22/2023
Deck receptacle 5th and 6th
|
||||
| Electrical Final Inspection | Partial Pass | 6/23/2023 (10:00 - 12:00) | 6/23/2023 (AM) | 06/23/2023 |
| Electrical Final Inspection | Partial Pass | 6/27/2023 (8:00 - 10:00) | 6/27/2023 (AM) | 06/27/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/27/2023
5 units on first floor.
|
||||
|
Miscellaneous/Other
Outstanding
06/27/2023
Pool bonding to pour border area. Need to have bonding wire in stairs moved to accessible location. railing cups require bonding, appear to be cut off from before.
|
||||
| Electrical Final Inspection | Failed | 6/28/2023 (12:30 - 2:30) | 6/28/2023 (PM) | 06/28/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/28/2023
4th floor deck receptacles - ok
|
||||
|
Miscellaneous/Other
Carried Forward
06/28/2023
GFCI required throughout common space areas servicing counters with sinks
|
||||
| Electrical Final Inspection | Partial Pass | 6/29/2023 (8:00 - 10:00) | 6/29/2023 (AM) | 06/30/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/30/2023
Double inspection, notes on second inspection.
|
||||
| Electrical Final Inspection | Failed | 6/29/2023 (10:00 - 12:00) | 6/29/2023 (AM) | 06/30/2023 |
|
Corrections:
Miscellaneous/Other
Carried Forward
06/30/2023
Maintenance bypass for generator requires proper labeling and annunciation per 700.3.
|
||||
|
Miscellaneous/Other
Carried Forward
06/30/2023
Access required to view fire pump installation.
|
||||
|
Miscellaneous/Other
Carried Forward
06/30/2023
Sky lounge area requires GFCI protection none found.
|
||||
| Electrical Final Inspection | Partial Pass | 7/3/2023 (2:30 - 3:30) | 7/3/2023 (PM) | 07/03/2023 |
|
Corrections:
Miscellaneous/Other
Outstanding
06/30/2023
Maintenance bypass for generator requires proper labeling and annunciation per 700.3.
|
||||
|
Miscellaneous/Other
Outstanding
06/30/2023
Access required to view fire pump installation.
|
||||
|
Miscellaneous/Other
Outstanding
06/30/2023
Sky lounge area requires GFCI protection none found.
|
||||
|
Miscellaneous/Other
Comment Only
07/03/2023
3rd floor deck receptacles except for the ones on Tony’s list that didn’t work or had no deck on yet.
|
||||
| Electrical Final Inspection | Partial Pass | 7/5/2023 (12:30 - 2:30) | 7/5/2023 (PM) | 07/05/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/05/2023
Progress inspection for finals - ok
|
||||
| Electrical Final Inspection | Partial Pass | 7/5/2023 (12:30 - 2:30) | 7/5/2023 (PM) | 07/05/2023 |
|
Corrections:
Miscellaneous/Other
Resolved
07/05/2023
GFCI required throughout common space areas servicing counters with sinks
|
||||
|
Miscellaneous/Other
Outstanding
07/05/2023
GEC connection in fire pump need to bond neutral.
|
||||
|
Miscellaneous/Other
Outstanding
07/05/2023
Labeling of all panels required
|
||||
|
Miscellaneous/Other
Outstanding
07/05/2023
1st floor deck receptacles required
|
||||
| Electrical Final Inspection | Partial Pass | 7/6/2023 (12:30 - 2:30) | 7/6/2023 (PM) | 07/06/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/06/2023
Deck receptacles for 6,5,4 complete.
|
||||
| Electrical Final Inspection | Partial Pass | 7/19/2023 (10:00 - 12:00) | 7/19/2023 (AM) | 07/19/2023 |
|
Corrections:
Miscellaneous/Other
Carried Forward
08/01/2023
Pool lights require proper grounding and inspection before being filled per 680.23B. Encapsulating required.
|
||||
|
Miscellaneous/Other
Carried Forward
08/01/2023
Sky deck receptacles require GFCI protection
|
||||
|
Miscellaneous/Other
Carried Forward
08/01/2023
Service and panel labeling required.
|
||||
|
Miscellaneous/Other
Carried Forward
08/01/2023
South 1st floor GFCI still need testing.
|
||||
| Electrical Final Inspection | Partial Pass | 8/2/2023 (8:00 - 10:00) | 8/2/2023 (AM) | 08/02/2023 |
|
Corrections:
Miscellaneous/Other
Carried Forward
08/08/2023
Pool lights require proper grounding and inspection before being filled per 680.23B. Encapsulating required.
|
||||
|
Miscellaneous/Other
Carried Forward
08/08/2023
Sky deck receptacles require GFCI protection
|
||||
|
Miscellaneous/Other
Carried Forward
08/08/2023
Service and panel labeling required.
|
||||
|
Miscellaneous/Other
Carried Forward
08/08/2023
South 1st floor GFCI still need testing.
|
||||
|
Miscellaneous/Other
Comment Only
08/02/2023
Deck outlet Unit 114 -Ok to move in.
|
||||
| Electrical Final Inspection | Partial Pass | 8/9/2023 (12:30 - 2:30) | 8/9/2023 (PM) | 08/09/2023 |
|
Corrections:
Miscellaneous/Other
Resolved
08/09/2023
Pool lights require proper grounding and inspection before being filled per 680.23B. Encapsulating required.
|
||||
|
Miscellaneous/Other
Carried Forward
08/16/2023
Sky deck receptacles require GFCI protection
|
||||
|
Miscellaneous/Other
Carried Forward
08/16/2023
Service and panel labeling required.
|
||||
|
Miscellaneous/Other
Carried Forward
08/16/2023
South 1st floor GFCI still need testing.
|
||||
|
Miscellaneous/Other
Comment Only
08/09/2023
Grounding of pool lights- ok
Wiring in pool equipment room partial- ok. Disconnects required for equipment.
|
||||
| Electrical Final Inspection | Failed | 8/17/2023 (12:30 - 2:30) | 8/17/2023 (PM) | 08/17/2023 |
|
Corrections:
Miscellaneous/Other
Carried Forward
08/17/2023
Sky deck receptacles require GFCI protection
|
||||
|
Miscellaneous/Other
Carried Forward
08/17/2023
Service and panel labeling required.
|
||||
|
Miscellaneous/Other
Resolved
08/17/2023
South 1st floor GFCI still need testing.
|
||||
|
Miscellaneous/Other
Carried Forward
08/17/2023
Pool equipment requires GFCI protection.
|
||||
|
Miscellaneous/Other
Carried Forward
08/17/2023
Pentair pool heater required proper NRTL listing. Could not find listing marks.
|
||||
| Electrical Final Inspection | Partial Pass | 8/29/2023 (12:30 - 2:30) | 8/29/2023 (PM) | 08/29/2023 |
|
Corrections:
Miscellaneous/Other
Carried Forward
09/07/2023
Sky deck receptacles require GFCI protection
|
||||
|
Miscellaneous/Other
Resolved
08/29/2023
Service and panel labeling required.
|
||||
|
Miscellaneous/Other
Carried Forward
09/07/2023
Pool equipment requires GFCI protection.
|
||||
|
Miscellaneous/Other
Resolved
08/29/2023
Pentair pool heater required proper NRTL listing. Could not find listing marks.
|
||||
|
Miscellaneous/Other
Carried Forward
09/07/2023
Deck box for pool lights required to be minimum 8” above high water line.
|
||||
|
Miscellaneous/Other
Carried Forward
09/07/2023
Placard annunciation horn for temp generator and maintenance switch. For its purpose.
Labeling shall comply 110.21 and 110.22.
|
||||
| Electrical Final Inspection | Partial Pass | 9/12/2023 (8:00 - 10:00) | 9/12/2023 (AM) | 09/12/2023 |
|
Corrections:
Miscellaneous/Other
Resolved
09/12/2023
Sky deck receptacles require GFCI protection
|
||||
|
Miscellaneous/Other
Resolved
09/12/2023
Pool equipment requires GFCI protection.
|
||||
|
Miscellaneous/Other
Resolved
09/12/2023
Deck box for pool lights required to be minimum 8” above high water line.
|
||||
|
Miscellaneous/Other
Carried Forward
09/25/2023
Placard annunciation horn for temp generator and maintenance switch. For its purpose.
Labeling shall comply 110.21 and 110.22.
|
||||
| Electrical Final Inspection | Passed | 9/27/2023 (10:00 - 12:00) | 9/27/2023 (AM) | 09/28/2023 |
|
Corrections:
Miscellaneous/Other
Resolved
09/28/2023
Placard annunciation horn for temp generator and maintenance switch. For its purpose.
Labeling shall comply 110.21 and 110.22.
|
||||
| Lighting Inspection | Passed | 10/10/2023 | ||
| Rohrs parking lot | ||||
| Electrical Final Inspection | Passed | 10/13/2023 | ||