PREL202116256
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Annual/Qtrly Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
04/20/2022
Progress inspections - for tool installations. See email correspondence for independent 3rd party evaluation requirements.
|
||||
Annual/Qtrly Inspection | Partial Pass | 03/08/2022 | ||
Corrections:
Miscellaneous/Other
Carried Forward
03/08/2022
Progress inspections - for tool installations. See email correspondence for independent 3rd party evaluation requirements.
|
||||
Annual/Qtrly Inspection | Partial Pass | 4/20/2022 (10:00 - 12:00) | 4/20/2022 (PM) | 04/20/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
04/20/2022
Progress inspections - for tool installations. See email correspondence for independent 3rd party evaluation requirements.
|
||||
Miscellaneous/Other
Comment Only
04/20/2022
Progress inspection- Independent 3rd party PE is in process of evaluation.
Discussed corrective actions.
|