Summary

PREL202202191
Electrical
Finaled
FINANCING PARTNERSHIP LP
Alteration/Repair/Replace
Work Description: Build-out of an existing warehouse space converting it to a photo studio/office/production area.
03/04/2022
03/08/2022
08/16/2023
02/17/2023

Locations

Permits

Permit Number: PREL202202191

Electrical
Finaled
03/08/2022
08/16/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 3/23/2022 (10:00 - 12:00) 3/23/2022 (AM) 03/23/2022
Corrections:


Miscellaneous/Other
Comment Only
03/23/2022
Wall ri

Electrical Rough-in Inspection Partial Pass 5/16/2022 (12:30 - 2:30) 5/16/2022 (PM) 05/16/2022
Corrections:


Miscellaneous/Other
Comment Only
05/16/2022
Wall RI for 3 sound stages- ok

Electrical Rough-in Inspection Partial Pass 6/7/2022 (10:00 - 12:00) 6/7/2022 (AM) 06/07/2022
Corrections:


Miscellaneous/Other
Comment Only
06/07/2022
Sound stage hard lid ri Make up wall ri

Electrical Rough-in Inspection Partial Pass 6/22/2022 (8:00 - 10:00) 6/22/2022 (AM) 06/22/2022
Corrections:


Miscellaneous/Other
Comment Only
06/22/2022
Wall ri

Electrical Rough-in Inspection Partial Pass 7/15/2022 (8:00 - 10:00) 7/15/2022 (AM) 07/15/2022
Corrections:


Miscellaneous/Other
Carried Forward
07/15/2022
Bathrooms wall ri Kitchen wall ri x 2

Electrical Rough-in Inspection Partial Pass 7/27/2022 (10:00 - 12:00) 7/27/2022 (AM) 07/27/2022
Corrections:


Miscellaneous/Other
Carried Forward
07/27/2022
Bathrooms wall ri Kitchen wall ri x 2

Miscellaneous/Other
Carried Forward
07/27/2022
Two bathroom ceiling ri Break room ceiling ri

Electrical Rough-in Inspection Partial Pass 8/8/2022 (8:00 - 10:00) 8/8/2022 (AM) 08/08/2022
Corrections:


Miscellaneous/Other
Carried Forward
08/08/2022
Bathrooms wall ri Kitchen wall ri x 2

Miscellaneous/Other
Carried Forward
08/08/2022
Two bathroom ceiling ri Break room ceiling ri

Miscellaneous/Other
Carried Forward
08/08/2022
Mezzanine wall ri

Electrical Rough-in Inspection Partial Pass 8/31/2022 (8:00 - 10:00) 8/31/2022 (AM) 08/31/2022
Corrections:


Miscellaneous/Other
Carried Forward
08/31/2022
Bathrooms wall ri Kitchen wall ri x 2

Miscellaneous/Other
Carried Forward
08/31/2022
Two bathroom ceiling ri Break room ceiling ri

Miscellaneous/Other
Carried Forward
08/31/2022
Mezzanine wall ri

Miscellaneous/Other
Carried Forward
08/31/2022
Mezzanine wall ri

Electrical Rough-in Inspection Partial Pass 9/20/2022 (8:00 - 10:00) 9/20/2022 (AM) 09/20/2022
Corrections:


Miscellaneous/Other
Carried Forward
09/20/2022
Bathrooms wall ri Kitchen wall ri x 2

Miscellaneous/Other
Carried Forward
09/20/2022
Two bathroom ceiling ri Break room ceiling ri

Miscellaneous/Other
Carried Forward
09/20/2022
Mezzanine wall ri

Miscellaneous/Other
Carried Forward
09/20/2022
Mezzanine wall ri

Miscellaneous/Other
Carried Forward
09/20/2022
Small office ceiling ri

Electrical Rough-in Inspection Passed 10/21/2022 (8:00 - 10:00) 10/21/2022 (AM) 10/21/2022
Corrections:


Miscellaneous/Other
Outstanding
09/20/2022
Bathrooms wall ri Kitchen wall ri x 2

Miscellaneous/Other
Outstanding
09/20/2022
Two bathroom ceiling ri Break room ceiling ri

Miscellaneous/Other
Outstanding
09/20/2022
Mezzanine wall ri

Miscellaneous/Other
Outstanding
09/20/2022
Mezzanine wall ri

Miscellaneous/Other
Outstanding
09/20/2022
Small office ceiling ri

Miscellaneous/Other
Outstanding
10/21/2022
Multiple office ceiling ri

Electrical Final Inspection Partial Pass 1/4/2023 (8:00 - 10:00) 1/4/2023 (AM) 01/04/2023
Corrections:


Miscellaneous/Other
Carried Forward
01/04/2023
Partial final

Electrical Final Inspection Partial Pass 1/6/2023 (8:00 - 10:00) 1/6/2023 (AM) 01/06/2023
Corrections:


Miscellaneous/Other
Carried Forward
01/06/2023
Partial final

Miscellaneous/Other
Carried Forward
01/06/2023
Partial final

Electrical Final Inspection Passed 2/17/2023 (12:30 - 2:30) 2/17/2023 (PM) 02/17/2023
Corrections:


Miscellaneous/Other
Outstanding
01/06/2023
Partial final

Miscellaneous/Other
Outstanding
01/06/2023
Partial final