PREL202203141
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 4/8/2022 (12:30 - 2:30) | 4/8/2022 (PM) | 04/08/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
04/08/2022
Partial wall ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 4/14/2022 (10:00 - 12:00) | 4/14/2022 (AM) | 04/14/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
04/14/2022
Partial wall ri
|
||||
Miscellaneous/Other
Comment Only
04/14/2022
Wall ri
|
||||
Electrical Rough-in Inspection | Passed | 4/28/2022 (8:00 - 10:00) | 4/28/2022 (AM) | 04/28/2022 |
Corrections:
Miscellaneous/Other
Outstanding
04/14/2022
Partial wall ri
|
||||
Miscellaneous/Other
Comment Only
04/28/2022
Wall ri phase ll
|
||||
Electrical Rough-in Inspection | Passed | 6/6/2022 (10:00 - 12:00) | 6/6/2022 (AM) | 06/06/2022 |
Corrections:
Miscellaneous/Other
Comment Only
06/06/2022
Ceiling ri
|
||||
Electrical Final Inspection | Failed | 6/29/2022 (12:30 - 2:30) | 6/29/2022 (PM) | 06/29/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
06/29/2022
Bathroom missing the switch.
Outlets not working on some floor boxes.
Open ground on monitor outlet - contractor knows which one since the rooms were not numbered yet.
Office furniture needs hooking up and tested for some being one circuit and some being 3 circuit feeds.
Panel schedule needs to be filled out and complete for circuits that is in suite 340.
|
||||
Electrical Final Inspection | Passed | 6/30/2022 (12:30 - 2:30) | 6/30/2022 (PM) | 06/30/2022 |
Corrections:
Miscellaneous/Other
Outstanding
06/29/2022
Bathroom missing the switch.
Outlets not working on some floor boxes.
Open ground on monitor outlet - contractor knows which one since the rooms were not numbered yet.
Office furniture needs hooking up and tested for some being one circuit and some being 3 circuit feeds.
Panel schedule needs to be filled out and complete for circuits that is in suite 340.
|