PREL202207633
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 10/19/2022 (8:00 - 10:00) | 10/19/2022 (AM) | 10/19/2022 |
R.I. Walls corridor only 5th floor. | ||||
Electrical Rough-in Inspection | Partial Pass | 10/27/2022 (8:00 - 10:00) | 10/27/2022 (AM) | 10/27/2022 |
R.I. Ceilings elevator lobby only | ||||
Electrical Rough-in Inspection | Passed | 11/16/2022 (8:00 - 10:00) | 11/16/2022 (AM) | 11/16/2022 |
R.I. Ceilings 5th Floor corridors. | ||||
Electrical Final Inspection | Passed | 11/18/2022 (8:00 - 10:00) | 11/18/2022 (AM) | 11/18/2022 |
5th floor corridor and elevator lobby. |