| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Partial Pass | 2/15/2023 (2:30 - 3:30) | 2/15/2023 (PM) | 02/15/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/15/2023
R.I. Underground in the garage basement area for 3/4 and 1 inch conduits.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/6/2023 (12:30 - 2:30) | 6/6/2023 (PM) | 06/06/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/06/2023
Site visit- walk site.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/13/2023 (2:30 - 3:30) | 6/13/2023 (PM) | 06/13/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/13/2023
R. I. Underground light base poles in parking lot.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/14/2023 (12:30 - 2:30) | 6/14/2023 (PM) | 06/14/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/14/2023
R. I. Underground for outside transformer and CT cabinet in parking lot area.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/21/2023 (12:30 - 2:30) | 6/21/2023 (PM) | 06/21/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/21/2023
R. I. 4th floor units-401,402,403,404,406,407,411
Need to get the sign off sheets for electrical R. I. On the general contractors unit sheets.
Will also be looking at the fire alarm wiring and fire stopping for all units at the R. I.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/22/2023 (12:30 - 2:30) | 6/22/2023 (PM) | 06/22/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/22/2023
R. I. Apartments for walls and ceilings- 461,461B,408,410,412,413,
414,415,416,417,418,420,
421,422,423,424,425,426,
427,428,429,430,432,433,
434,462,463,469,472
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/26/2023 (12:30 - 2:30) | 6/26/2023 (PM) | 06/26/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/26/2023
R. I. Apartments 436,437,439,441.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/28/2023 (8:00 - 10:00) | 6/28/2023 (AM) | 06/28/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/28/2023
R. I. 4th floor rooms 435, 437, 473, 475, 476.
All of 4th floor done for R. I..
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/12/2023 (12:30 - 2:30) | 7/12/2023 (PM) | 07/12/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/12/2023
R. I. 3rd floor units - 301,302,303,304,305,306,307,308,308,311,313,360,361.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/13/2023 (10:00 - 12:00) | 7/13/2023 (AM) | 07/13/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/13/2023
3rd floor units- 310,312,314,315,317,319,321,323,324,325,326,327,328,362,363,369,372,373(a,b),392.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/14/2023 (10:00 - 12:00) | 7/14/2023 (AM) | 07/14/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/14/2023
R. I. 3rd floor units- 316,318,320,322,326,329,330,331,332,333,334,335,336,337,339,341,374,375.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/27/2023 (10:00 - 12:00) | 7/27/2023 (AM) | 07/27/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/27/2023
R. I. Apts. 201-215, 217,219, and areas 260,261,290.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/31/2023 (10:00 - 12:00) | 7/31/2023 (AM) | 07/31/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/31/2023
R. I. Rooms - 216,218, 220-230, 232,262,263,269,273.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/1/2023 (10:00 - 12:00) | 8/1/2023 (AM) | 08/01/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/01/2023
R. I. 2nd floor units - 233,234,235,236,237,239,241,274,275,stairway B.
Also mock up rooms1st floor- 101,103.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/10/2023 (10:00 - 12:00) | 8/10/2023 (AM) | 08/10/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/10/2023
4th floor R. I. Ceilings in 8 Studio apartments for access panel and lights.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/16/2023 (2:30 - 3:30) | 8/16/2023 (PM) | 08/16/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/16/2023
R. I. Underground transformer on south side of the building.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/22/2023 (12:30 - 2:30) | 8/22/2023 (PM) | 08/22/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/22/2023
R. I. First floor Rooms 102,104,105,106,107,108,
109,110,111,112,113,115,117
161,190A.
Third floor- 10 rooms R.I.Studio ceilings.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/23/2023 (12:30 - 2:30) | 8/23/2023 (PM) | 08/23/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/23/2023
R. I. Units 114,119, 124 thru 135, 152, 162.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/24/2023 (12:30 - 2:30) | 8/24/2023 (PM) | 08/24/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/24/2023
R.I. Rooms - 136,137,139,141,150,151,
153,154,156,157,158,163,
164,170,172,173,174,175,
191A.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/5/2023 (12:30 - 2:30) | 9/5/2023 (PM) | 09/05/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/05/2023
R. I. Ceilings 2nd floor 10 studio apartments for hard lid ceiling.
Also units 1st floor 165-168- R. I. Walls and ceilings.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/3/2023 (10:00 - 12:00) | 10/3/2023 (AM) | 10/03/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/03/2023
R. I. 1st floor dropped ceiling 5 units on north side.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/12/2023 (10:00 - 12:00) | 10/12/2023 (AM) | 10/12/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/12/2023
R. I. Hard lid ceilings 1st floor.
Notified Xcel Energy for meters in 1st and 3rd floors meter bank rooms.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/16/2023 (12:30 - 2:30) | 10/16/2023 (PM) | 10/16/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/16/2023
R. I. 1st floor hard lid ceilings, offices and reception area.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 11/13/2023 (10:00 - 12:00) | 11/13/2023 (AM) | 11/13/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/13/2023
R. I. Service North side of the building.
|
||||
| Electrical Final Inspection | Partial Pass | 12/18/2023 (8:00 - 10:00) | 12/18/2023 (AM) | 12/18/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/18/2023
Partial final for 4th floor north side of building units - 401,402,403,404,406,408,409,413.
|
||||
| Electrical Final Inspection | Partial Pass | 12/20/2023 | 12/20/2023 (AM) | 12/20/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/20/2023
R. I. Outside canopy lights hard lid ceilings in main entrance.
Partial finals Units 3rd floor- 301,302,303,304,305,306,308,309,311,313.
|
||||
| Electrical Final Inspection | Partial Pass | 12/26/2023 (8:00 - 10:00) | 12/26/2023 (AM) | 12/26/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/26/2023
Finals for units 2nd floor- 201,202,203,204,205,206,209,211.
|
||||
| Electrical Final Inspection | Partial Pass | 12/27/2023 (8:00 - 10:00) | 12/27/2023 (AM) | 12/27/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/27/2023
Final units 101,102, 103,104, 105, 106,108,109,111,113, 208.
|
||||
| Electrical Final Inspection | Partial Pass | 12/28/2023 (8:00 - 10:00) | 12/28/2023 (AM) | 12/28/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/28/2023
Final Units 4th floor South side of building- 410,412,414,415,416,417,
418,419,420,421,422,423,
424,425,427.
|
||||
| Electrical Final Inspection | Partial Pass | 12/29/2023 (8:00 - 10:00) | 12/29/2023 (AM) | 12/29/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/29/2023
Final units 4th floor- 411,426,428,429,430,431,432,433,434,436,437,439,441.
|
||||
| Lighting Inspection Sign | Passed | 12/30/2023 | ||
| Apartments Signs 125 ir 300 | ||||
| Electrical Final Inspection | Partial Pass | 1/2/2024 (8:00 - 10:00) | 1/2/2024 (AM) | 01/02/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/02/2024
Final units - 310,312,314,315,
316,317,319,320,321,322,
323,324,325,326.
|
||||
| Electrical Final Inspection | Partial Pass | 1/3/2024 (10:00 - 12:00) | 1/3/2024 (AM) | 01/03/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/03/2024
Final units - 327,328,329,330,331,332,
333,334,336,339,341.
|
||||
| Electrical Final Inspection | Partial Pass | 1/4/2024 (8:00 - 10:00) | 1/4/2024 (AM) | 01/04/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/04/2024
Final units- 210,212,214,215,
216,217,219,220,221,222,
223,225,226,227,228.
|
||||
| Electrical Final Inspection | Partial Pass | 1/8/2024 (8:00 - 10:00) | 1/8/2024 (AM) | 01/08/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/08/2024
Final units 229,230,231,232,233,234,
237,239,241.
|
||||
| Electrical Final Inspection | Partial Pass | 1/9/2024 (8:00 - 10:00) | 1/9/2024 (AM) | 01/09/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/09/2024
Final units- 110,112,114,115,
117,119,124,125,126,127,128
|
||||
| Electrical Final Inspection | Partial Pass | 1/10/2024 (8:00 - 10:00) | 1/10/2024 (AM) | 01/10/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/10/2024
Final rooms 4th floor 461A, 462,462B, 463,469,472,475, elevator lobby and corridors.
3rd floor 361,362,363,369,375, elevator lobby, and corridors.
|
||||
| Electrical Final Inspection | Partial Pass | 1/11/2024 (8:00 - 10:00) | 1/11/2024 (AM) | 01/11/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/11/2024
Final units- 129,130,131,132
133,136,139.
|
||||
| Electrical Final Inspection | Partial Pass | 1/16/2024 (8:00 - 10:00) | 1/16/2024 (AM) | 01/16/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/16/2024
Final units - 407,435,337,335,307,207,218,235,274,275,263,272,269,260,261,262,stairwells and 2nd floor elevator lobby.
|
||||
| Electrical Final Inspection | Partial Pass | 1/23/2024 (12:30 - 2:30) | 1/23/2024 (PM) | 01/23/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/23/2024
Final units 107,113,134,137.
1st floor community room and bathrooms, conference rooms, dog wash room, yoga and workout room and some electrical rooms throughout the building.
|
||||
| Electrical Final Inspection | Partial Pass | 1/29/2024 (12:30 - 2:30) | 1/29/2024 (PM) | 01/29/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/29/2024
Need to clean electrical rooms.
Strap conduit in garage area.
Need GFCI outlets by outside grill area.
|
||||
| Electrical Final Inspection | Passed | 2/5/2024 (8:00 - 10:00) | 2/5/2024 (AM) | 02/05/2024 |