PREL202210942
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Final Inspection | Pending | |||
| Electrical Rough-in Inspection | Passed | 8/7/2023 (12:30 - 2:30) | 8/7/2023 (PM) | 08/07/2023 |
| Electrical Final Inspection | Partial Pass | 8/7/2023 (12:30 - 2:30) | 8/7/2023 (PM) | 08/07/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/07/2023
Contacted Xcel Energy about metering a 600 amp 277/ 480 V Service for EV chargers.
|
||||