PREL202215654
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 2/3/2023 (10:00 - 12:00) | 2/3/2023 (AM) | 02/03/2023 |
Corrections:
Miscellaneous/Other
Comment Only
02/03/2023
R.I. Walls only Suite #100 building 1650 South Point.
|
||||
Electrical Rough-in Inspection | Passed | 2/21/2023 (8:00 - 10:00) | 2/21/2023 (AM) | 02/21/2023 |
Corrections:
Miscellaneous/Other
Comment Only
02/21/2023
R.I. Ceilings for lights only.
Thermostats still above ceiling not fished down yet.
|
||||
Electrical Final Inspection | Partial Pass | 3/22/2023 (10:00 - 12:00) | 3/22/2023 (AM) | 03/22/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
03/22/2023
Temporary final only for Suite 100.
Need modular furniture installed and powered up for final inspection.
|
||||
Electrical Final Inspection | Passed | 4/4/2023 (10:00 - 12:00) | 4/4/2023 (AM) | 04/04/2023 |
Corrections:
Miscellaneous/Other
Outstanding
03/22/2023
Temporary final only for Suite 100.
Need modular furniture installed and powered up for final inspection.
|