PREL202300116
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 2/3/2023 (10:00 - 12:00) | 2/3/2023 (AM) | 02/03/2023 |
Corrections:
Miscellaneous/Other
Comment Only
02/03/2023
R.I. Walls only next to CSL plasma building.
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/21/2023 (12:30 - 2:30) | 2/21/2023 (PM) | 02/21/2023 |
Corrections:
Miscellaneous/Other
Comment Only
02/21/2023
Service main switch gear 400 amp 3 phase contacted Xcel Energy for meter install.
|
||||
Electrical Rough-in Inspection | Passed | 3/16/2023 (10:00 - 12:00) | 3/16/2023 (AM) | 03/16/2023 |
Corrections:
Miscellaneous/Other
Comment Only
03/16/2023
R. I. Ceilings- Ok
|
||||
Electrical Final Inspection | Passed | 4/18/2023 (12:30 - 2:30) | 4/18/2023 (PM) | 04/18/2023 |