Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 2/14/2023 (10:00 - 12:00) | 2/14/2023 (AM) | 02/14/2023 |
Corrections:
Miscellaneous/Other
Comment Only
02/14/2023
Wall RI- ok
Still need above ceiling. Also need FA and temp control permits before ceiling approval.
|
||||
Electrical Rough-in Inspection | Passed w/ Conditions | 3/21/2023 (10:00 - 12:00) | 3/21/2023 (AM) | 03/21/2023 |
Corrections:
Miscellaneous/Other
Comment Only
03/21/2023
Above ceiling- ok
Talked to contractor about a couple open boxes and wiring support. Ok to cover when corrected.
|
||||
Electrical Final Inspection | Failed | 5/4/2023 (8:00 - 10:00) | 5/4/2023 (AM) | 05/04/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
05/04/2023
Power missing in multiple areas.
|
||||
Electrical Final Inspection | Passed | 5/5/2023 (8:00 - 10:00) | 5/5/2023 (AM) | 05/05/2023 |
Corrections:
Miscellaneous/Other
Resolved
05/05/2023
Power missing in multiple areas.
|
||||
Miscellaneous/Other
Comment Only
05/05/2023
Issues resolved- ok