PREL202300729
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Failed | 2/1/2023 (10:00 - 12:00) | 2/1/2023 (AM) | 02/01/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
02/01/2023
Transformer secondary conductors require protection within 25’ per NEC 240.21C
|
||||
Electrical Final Inspection | Passed | 2/16/2023 (8:00 - 10:00) | 2/16/2023 (AM) | 02/16/2023 |
Corrections:
Miscellaneous/Other
Comment Only
02/16/2023
Disconnect added for xformer secondary conductors. - ok
|