PREL202302144
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Final Inspection | Pending | |||
| Electrical Rough-in Inspection | Failed | 5/4/2023 (2:30 - 3:30) | 5/4/2023 (PM) | 05/04/2023 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/04/2023
R. I. Ceilings- Suite 380 failed because need bushings on 2 of the 7 thermostats on their conduits.
Also never called for R. I. Inspection before the ceiling tiles were to be installed.
Also do not put ceiling tiles in those locations and call for a reinspection when fixed.
|
||||
| Electrical Rough-in Inspection | Passed | 5/9/2023 (8:00 - 10:00) | 5/9/2023 (AM) | 05/09/2023 |
|
Corrections:
Miscellaneous/Other
Resolved
05/09/2023
R. I. Ceilings- Suite 380 failed because need bushings on 2 of the 7 thermostats on their conduits.
Also never called for R. I. Inspection before the ceiling tiles were to be installed.
Also do not put ceiling tiles in those locations and call for a reinspection when fixed.
|
||||
|
Miscellaneous/Other
Comment Only
05/09/2023
Corrections were resolved.
|
||||
| Electrical Rough-in Inspection | Passed | 5/30/2023 (12:30 - 2:30) | 5/30/2023 (PM) | 05/30/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/30/2023
R. I. Ceilings Suite 325 thermostats and VAV upgrades.
|
||||
| Electrical Rough-in Inspection | Passed | 6/21/2023 (2:30 - 3:30) | 6/21/2023 (PM) | 06/21/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/21/2023
R. I. Ceilings Suite 320 for VAV upgrades.
|
||||