PREL202302535
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Final Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
03/24/2023
New equipment requires NRTL listings or 3rd party review.
|
||||
Electrical Rough-in Inspection | Passed | 3/24/2023 (8:00 - 10:00) | 3/24/2023 (AM) | 03/24/2023 |
Corrections:
Miscellaneous/Other
Comment Only
03/24/2023
New 60a circuit to new equipment- ok
|
||||
Electrical Final Inspection | Failed | 3/24/2023 (8:00 - 10:00) | 3/24/2023 (AM) | 03/24/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
03/24/2023
New equipment requires NRTL listings or 3rd party review.
|