Permit Application Status

PREL202304706


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202304706
Electrical
Finaled
MSP BLN OFFICE LLC
Alteration/Repair/Replace
New lighting for 6th level corridoe and restrooms. (11) ceiling mounted OCC sensors, (23) LED recess cans, (14) 2x2 LED lights, New lamps for the elevator cove lighting, 6 EM/EX lights. (3) gen purpose duplex, (2) GFCI receptacles.
05/08/2023
05/11/2023
02/04/2024
08/08/2023

Locations

Permits

Permit Number: PREL202304706

Electrical
Finaled
05/11/2023
02/04/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Passed 5/30/2023 (2:30 - 3:30) 5/30/2023 (PM) 05/30/2023
Corrections:


Miscellaneous/Other
Comment Only
05/30/2023
Above ceiling- ok

Electrical Final Inspection Not Ready 6/27/2023 (2:30 - 3:30) 6/27/2023 (PM) 06/27/2023
Contractor called to cancel today's inspection. [jsmidt @ 06/27/2023 8:10 AM]
Corrections:


Miscellaneous/Other
Carried Forward
06/27/2023
Inspection canceled

Electrical Final Inspection Failed 6/28/2023 (12:30 - 2:30) 6/28/2023 (PM) 06/28/2023
Corrections:


Miscellaneous/Other
Carried Forward
06/28/2023
GFCI required for bathroom women’s restroom and drinking fountain 6th floor.

Miscellaneous/Other
Carried Forward
06/28/2023
GFCI for drinking fountains required. Verify receptacle in hall polarity.

Electrical Final Inspection Passed 8/8/2023 (2:30 - 3:30) 8/8/2023 (PM) 08/08/2023
Corrections:


Miscellaneous/Other
Resolved
08/08/2023
GFCI required for bathroom women’s restroom and drinking fountain 6th floor.

Miscellaneous/Other
Resolved
08/08/2023
GFCI for drinking fountains required. Verify receptacle in hall polarity.