PREL202306952
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Partial Pass | 7/11/2023 (8:00 - 10:00) | 7/11/2023 (AM) | 07/11/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/11/2023
Whole house ri
Fan boxes needed in dining room and dinette
Master bathroom floor heat stat ok
Floor heat inspection needed before tile
Service not ready
Siding ri ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/10/2023 (12:30 - 2:30) | 8/10/2023 (PM) | 08/10/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/10/2023
R. I. Infloor heat in 2nd floor bathroom.- Ok
|
||||
| Electrical Rough-in Inspection | Passed | 10/23/2023 (10:00 - 12:00) | 10/23/2023 (AM) | 10/23/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/23/2023
All R. I. Items for partial pass -Ok.
Contacted Xcel Energy also about the U.G. Service.
|
||||
| Electrical Final Inspection | Passed | 10/23/2023 (10:00 - 12:00) | 10/23/2023 (AM) | 10/23/2023 |