PREL202308620
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Failed | 8/11/2023 (2:30 - 3:30) | 8/11/2023 (PM) | 08/11/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
08/11/2023
Break room wall covered before RI complete needs to be opened for viewing.
|
||||
Miscellaneous/Other
Comment Only
08/11/2023
3 receptacles in wall by pick up area- ok
|
||||
Miscellaneous/Other
Comment Only
08/11/2023
Temp transformer install- ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 8/15/2023 (8:00 - 10:00) | 8/15/2023 (AM) | 08/15/2023 |
Corrections:
Miscellaneous/Other
Comment Only
08/15/2023
Wall RI break area- ok
|
||||
Electrical Final Inspection | Partial Pass | 8/17/2023 (7:00 - 8:00) | 8/17/2023 (AM) | 08/17/2023 |
Corrections:
Miscellaneous/Other
Comment Only
08/17/2023
Break area final- ok
|
||||
Miscellaneous/Other
Comment Only
08/17/2023
Wall RI for bathroom area - ok
|
||||
Miscellaneous/Other
Carried Forward
08/17/2023
Approved handle ties required to be installed on the CB with multi wire circuits.
|
||||
Miscellaneous/Other
Carried Forward
08/17/2023
Lite mirrors to be installed require to have proper NRTL listing and labeling.
|
||||
Electrical Final Inspection | Partial Pass | 9/7/2023 (7:00 - 8:00) | 9/7/2023 (AM) | 09/07/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
09/07/2023
Approved handle ties required to be installed on the CB with multi wire circuits.
|
||||
Miscellaneous/Other
Resolved
09/07/2023
Lite mirrors to be installed require to have proper NRTL listing and labeling.
|
||||
Miscellaneous/Other
Comment Only
09/07/2023
Front bathroom final- ok
|
||||
Electrical Rough-in Inspection | Passed | 9/15/2023 (7:00 - 8:00) | 9/15/2023 (AM) | 09/15/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/15/2023
Back restroom RI- ok
|
||||
Electrical Final Inspection | Partial Pass | 9/27/2023 (7:00 - 8:00) | 9/27/2023 (AM) | 09/28/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
09/28/2023
Approved handle ties required to be installed on the CB with multi wire circuits.
|
||||
Miscellaneous/Other
Comment Only
09/28/2023
Rear bathroom finals- ok
|
||||
Electrical Rough-in Inspection | Passed | 9/27/2023 (8:00 - 10:00) | 9/27/2023 (AM) | 09/28/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/28/2023
RI for front transformer connections - ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/6/2023 (7:00 - 8:00) | 10/6/2023 (AM) | 10/06/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/06/2023
Cooler/ freezer install- ok
Power pole for POS - ok
Walls and above ceilings for optical- ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/13/2023 (7:00 - 8:00) | 10/13/2023 (AM) | 10/13/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/13/2023
Final optical area- ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/19/2023 (7:00 - 8:00) | 10/19/2023 (AM) | 10/19/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/19/2023
Temp pharmacy area- ok
|
||||
Electrical Rough-in Inspection | Passed | 10/27/2023 (7:00 - 8:00) | 10/27/2023 (AM) | 10/27/2023 |
Corrections:
Miscellaneous/Other
Resolved
10/27/2023
Break room wall covered before RI complete needs to be opened for viewing.
|
||||
Miscellaneous/Other
Comment Only
10/27/2023
Pharmacy extension area - ok
|
||||
Electrical Final Inspection | Partial Pass | 11/3/2023 (7:00 - 8:00) | 11/3/2023 (AM) | 11/03/2023 |
Corrections:
Miscellaneous/Other
Resolved
11/03/2023
Approved handle ties required to be installed on the CB with multi wire circuits.
|
||||
Miscellaneous/Other
Carried Forward
11/03/2023
GFCI required for receptacles added in cart area.
Still have door install in pick up area.
|
||||
Electrical Final Inspection | Passed | 12/12/2023 (8:00 - 10:00) | 12/12/2023 (AM) | 12/12/2023 |
11/16 inspection cancelled; will call back when ready. thx vm 11/15/23 | ||||
Corrections:
Miscellaneous/Other
Resolved
12/12/2023
GFCI required for receptacles added in cart area.
Still have door install in pick up area.
|
||||
Miscellaneous/Other
Comment Only
12/12/2023
Door install and GFCI- ok
|