PREL202308658
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Failed | 8/17/2023 (10:00 - 12:00) | 8/17/2023 (AM) | 08/17/2023 |
|
Corrections:
Miscellaneous/Other
Carried Forward
08/17/2023
Above ceiling on 2nd and 3rd floors. Required low voltage and communication wiring to be properly demoed and properly supported.
|
||||
|
Miscellaneous/Other
Carried Forward
08/17/2023
Verify proper EM lighting in elevator lobby areas.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/13/2023 (10:00 - 12:00) | 9/13/2023 (AM) | 09/13/2023 |
|
Corrections:
Miscellaneous/Other
Carried Forward
09/13/2023
Above ceiling on 2nd and 3rd floors. Required low voltage and communication wiring to be properly demoed and properly supported.
|
||||
|
Miscellaneous/Other
Carried Forward
09/13/2023
Verify proper EM lighting in elevator lobby areas.
|
||||
|
Miscellaneous/Other
Comment Only
09/13/2023
Bathroom ceilings second and fourth.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 11/7/2023 (8:00 - 10:00) | 11/7/2023 (AM) | 11/07/2023 |
|
Corrections:
Miscellaneous/Other
Resolved
11/07/2023
Above ceiling on 2nd and 3rd floors. Required low voltage and communication wiring to be properly demoed and properly supported.
|
||||
|
Miscellaneous/Other
Resolved
11/07/2023
Verify proper EM lighting in elevator lobby areas.
|
||||
| Electrical Final Inspection | Partial Pass | 11/7/2023 (8:00 - 10:00) | 11/7/2023 (AM) | 11/07/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/07/2023
Finals for 4- ok
|
||||
|
Miscellaneous/Other
Carried Forward
11/07/2023
GFCI not functioning on 2 in bathrooms.
|
||||
| Electrical Rough-in Inspection | Passed | 11/16/2023 (12:30 - 2:30) | 11/16/2023 (PM) | 11/16/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/16/2023
Wall RI and above ceiling- ok
|
||||
| Electrical Rough-in Inspection | Passed | 12/5/2023 (10:00 - 12:00) | 12/5/2023 (AM) | 12/05/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/05/2023
1st floor bathroom ceilings- ok
|
||||
| Electrical Final Inspection | Passed | 1/5/2024 (10:00 - 12:00) | 1/5/2024 (AM) | 01/05/2024 |
|
Corrections:
Miscellaneous/Other
Resolved
01/05/2024
GFCI not functioning on 2 in bathrooms.
|
||||
|
Miscellaneous/Other
Comment Only
01/05/2024
GFCI for bathroom areas and halls
|
||||