PREL202311560
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 11/7/2023 (12:30 - 2:30) | 11/7/2023 (PM) | 11/07/2023 |
Corrections:
Miscellaneous/Other
Comment Only
11/07/2023
R. I. Ceilings elevator lobby hard lid ceilings 7th floor 3600 Building.
|
||||
Electrical Rough-in Inspection | Passed | 11/13/2023 (8:00 - 10:00) | 11/13/2023 (AM) | 11/13/2023 |
Corrections:
Miscellaneous/Other
Comment Only
11/13/2023
R. I. Hallway 7th floor- Ok
|
||||
Electrical Final Inspection | Passed | 11/21/2023 (10:00 - 12:00) | 11/21/2023 (AM) | 11/21/2023 |