PREL202311770
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Lighting Inspection | Passed | 12/30/2023 | ||
Parking lot Clover shopping center Wells side | ||||
Electrical Rough-in Inspection | Passed | 1/2/2024 (AM) | 01/02/2024 | |
Electrical Final Inspection | Not Ready | 1/2/2024 (AM) | 01/02/2024 | |
Corrections:
Miscellaneous/Other
Comment Only
01/02/2024
Not done, still waiting on parts.
|
||||
Electrical Final Inspection | Passed | 2/28/2025 (12:30 - 2:30) | 2/28/2025 (PM) | 02/28/2025 |
Corrections:
Miscellaneous/Other
Outstanding
02/28/2025
West half of parking lot- the electrician only replace the light heads.
East half of parking lot- they installed new poles and lights
Ok
|