PREL202312112
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Passed | 11/15/2023 (10:00 - 12:00) | 11/15/2023 (AM) | 11/15/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/15/2023
Contacted Xcel Energy for transformer for a 200 amp 277/480 volt 3 phase service.
U. G. Trench passed inspection.
|
||||
| Electrical Final Inspection | Passed | 5/30/2024 (10:00 - 12:00) | 5/30/2024 (AM) | 05/30/2024 |