Permit Application Status

PREL202313695


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202313695
Electrical
Finaled
GKII NORTHLAND CENTER LLC
Alteration/Repair/Replace
Electrical work for remodel of existing space including adding (30) 20a circuits.
11/08/2023
12/08/2023
09/07/2024
03/11/2024

Locations

Permits

Permit Number: PREL202313695

Electrical
Finaled
12/08/2023
09/07/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 12/18/2023 (10:00 - 12:00) 12/18/2023 (AM) 12/18/2023
Corrections:


Miscellaneous/Other
Comment Only
12/18/2023
R. I. Walls only 3rd floor.

Electrical Rough-in Inspection Partial Pass 1/5/2024 (8:00 - 10:00) 1/5/2024 (AM) 01/05/2024
Corrections:


Miscellaneous/Other
Comment Only
01/05/2024
R. I. Ceilings north end of 3rd floor.

Electrical Rough-in Inspection Partial Pass 1/11/2024 (10:00 - 12:00) 1/11/2024 (AM) 01/11/2024
Corrections:


Miscellaneous/Other
Comment Only
01/11/2024
R. I. Walls north side 2 offices.

Electrical Rough-in Inspection Passed 1/19/2024 (8:00 - 10:00) 1/19/2024 (AM) 01/19/2024
Corrections:


Miscellaneous/Other
Comment Only
01/19/2024
R. I. Ceilings north side offices.

Electrical Final Inspection Partial Pass 1/25/2024 (10:00 - 12:00) 1/25/2024 (AM) 01/25/2024
Corrections:


Miscellaneous/Other
Comment Only
01/25/2024
North side of 3rd floor final only for offices and modular powered furniture.

Electrical Rough-in Inspection Passed 2/20/2024 (12:30 - 2:30) 2/20/2024 (PM) 02/20/2024
Corrections:


Miscellaneous/Other
Comment Only
02/20/2024
R. I. Ceilings 3rd floor.

Electrical Final Inspection Partial Pass 2/21/2024 (8:00 - 10:00) 2/21/2024 (AM) 02/21/2024
Corrections:


Miscellaneous/Other
Comment Only
02/21/2024
Final all areas of 3rd floor- still missing 30 lights on the south side of the building. Will give temporary final now and main final inspection when the lights are installed.

Electrical Final Inspection Passed 3/11/2024 (8:00 - 10:00) 3/11/2024 (AM) 03/11/2024