Electrical Rough-in Inspection | Partial Pass | 5/10/2024 (10:00 - 12:00) | 5/10/2024 (AM) | 05/10/2024 |
Corrections:
Miscellaneous/Other
Comment Only
05/10/2024
Wall RI only- ok
|
||||
Electrical Rough-in Inspection | Passed | 5/23/2024 (12:30 - 2:30) | 5/23/2024 (PM) | 05/23/2024 |
Corrections:
Miscellaneous/Other
Comment Only
05/23/2024
Above ceilings ok
|
||||
Electrical Final Inspection | Partial Pass | 6/12/2024 (12:30 - 2:30) | 6/12/2024 (PM) | 06/12/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
06/12/2024
Fixtures installs still needed. Temporary blanked off.
Entry tunnel needs listed lighting updates.
|
||||
Miscellaneous/Other
Comment Only
06/12/2024
|
||||
Electrical Final Inspection | Passed | 6/21/2024 (8:00 - 10:00) | 6/21/2024 (AM) | 06/21/2024 |
Corrections:
Miscellaneous/Other
Resolved
06/21/2024
Fixtures installs still needed. Temporary blanked off.
Entry tunnel needs listed lighting updates.
|
||||
Miscellaneous/Other
Comment Only
06/21/2024
Lighting tunnel all class 2 protected.