PREL202406461
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Failed | 5/21/2024 (12:30 - 2:30) | 5/21/2024 (PM) | 05/21/2024 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/21/2024
Finish Grounding electrodes to transformer.
Bonding of transformer required.
|
||||
|
Miscellaneous/Other
Carried Forward
05/21/2024
Supply side bonding jumpers required to be installed. To disconnect.
|
||||
|
Miscellaneous/Other
Carried Forward
05/21/2024
Finish all connections and grounding connections in all panel boards.
|
||||
|
Miscellaneous/Other
Carried Forward
05/21/2024
Verify all available fault currents and properly label per NEC requirements.
|
||||
| Electrical Rough-in Inspection | Failed | 5/24/2024 (12:30 - 2:30) | 5/24/2024 (PM) | 05/24/2024 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/24/2024
Finish Grounding electrodes to transformer.
Bonding of transformer required.
|
||||
|
Miscellaneous/Other
Carried Forward
05/24/2024
Supply side bonding jumpers required to be installed. To disconnect.
|
||||
|
Miscellaneous/Other
Carried Forward
05/24/2024
Finish all connections and grounding connections in all panel boards.
|
||||
|
Miscellaneous/Other
Carried Forward
05/24/2024
Verify all available fault currents and properly label per NEC requirements.
|
||||
|
Miscellaneous/Other
Carried Forward
05/24/2024
Inspection cancelled equipment not ready
|
||||
| Electrical Final Inspection | Not Ready | 5/24/2024 (12:30 - 2:30) | 5/24/2024 (PM) | 05/24/2024 |
| Electrical Rough-in Inspection | Passed | 5/28/2024 (12:30 - 2:30) | 5/28/2024 (PM) | 05/28/2024 |
|
Corrections:
Miscellaneous/Other
Resolved
05/28/2024
Finish Grounding electrodes to transformer.
Bonding of transformer required.
|
||||
|
Miscellaneous/Other
Resolved
05/28/2024
Supply side bonding jumpers required to be installed. To disconnect.
|
||||
|
Miscellaneous/Other
Resolved
05/28/2024
Finish all connections and grounding connections in all panel boards.
|
||||
|
Miscellaneous/Other
Resolved
05/28/2024
Verify all available fault currents and properly label per NEC requirements.
|
||||
|
Miscellaneous/Other
Resolved
05/28/2024
Inspection cancelled equipment not ready
|
||||
| Electrical Final Inspection | Passed | 5/28/2024 (2:30 - 3:30) | 5/28/2024 (PM) | 05/28/2024 |