PREL202406461
Electrical
Finaled
;
Alteration/Repair/Replace
Adding Service needed to power 4 - 10 racks of computer servers.
05/17/2024
05/20/2024
11/24/2024
05/28/2024

Locations

Permits

Permit Number: PREL202406461

Electrical
Finaled
05/20/2024
11/24/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Failed 5/21/2024 (12:30 - 2:30) 5/21/2024 (PM) 05/21/2024
Corrections:


Miscellaneous/Other
Carried Forward
05/21/2024
Finish Grounding electrodes to transformer. Bonding of transformer required.

Miscellaneous/Other
Carried Forward
05/21/2024
Supply side bonding jumpers required to be installed. To disconnect.

Miscellaneous/Other
Carried Forward
05/21/2024
Finish all connections and grounding connections in all panel boards.

Miscellaneous/Other
Carried Forward
05/21/2024
Verify all available fault currents and properly label per NEC requirements.

Electrical Rough-in Inspection Failed 5/24/2024 (12:30 - 2:30) 5/24/2024 (PM) 05/24/2024
Corrections:


Miscellaneous/Other
Carried Forward
05/24/2024
Finish Grounding electrodes to transformer. Bonding of transformer required.

Miscellaneous/Other
Carried Forward
05/24/2024
Supply side bonding jumpers required to be installed. To disconnect.

Miscellaneous/Other
Carried Forward
05/24/2024
Finish all connections and grounding connections in all panel boards.

Miscellaneous/Other
Carried Forward
05/24/2024
Verify all available fault currents and properly label per NEC requirements.

Miscellaneous/Other
Carried Forward
05/24/2024
Inspection cancelled equipment not ready

Electrical Final Inspection Not Ready 5/24/2024 (12:30 - 2:30) 5/24/2024 (PM) 05/24/2024
Electrical Rough-in Inspection Passed 5/28/2024 (12:30 - 2:30) 5/28/2024 (PM) 05/28/2024
Corrections:


Miscellaneous/Other
Resolved
05/28/2024
Finish Grounding electrodes to transformer. Bonding of transformer required.

Miscellaneous/Other
Resolved
05/28/2024
Supply side bonding jumpers required to be installed. To disconnect.

Miscellaneous/Other
Resolved
05/28/2024
Finish all connections and grounding connections in all panel boards.

Miscellaneous/Other
Resolved
05/28/2024
Verify all available fault currents and properly label per NEC requirements.

Miscellaneous/Other
Resolved
05/28/2024
Inspection cancelled equipment not ready

Electrical Final Inspection Passed 5/28/2024 (2:30 - 3:30) 5/28/2024 (PM) 05/28/2024