PREL202407955
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Final Inspection | Partial Pass | 8/5/2024 (12:30 - 2:30) | 8/5/2024 (PM) | 08/05/2024 |
Corrections:
Miscellaneous/Other
Comment Only
08/05/2024
Transformer install- ok
Tool evaluation required.
|
||||
Electrical Final Inspection | Passed | 11/01/2024 |