PREL202408199
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Partial Pass | 8/6/2024 (10:00 - 12:00) | 8/6/2024 (AM) | 08/06/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/06/2024
R. I. 2nd floor deck level west side of building- 1 of 2 pours on each floor. Ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/20/2024 (7:00 - 8:00) | 8/20/2024 (AM) | 08/20/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/20/2024
R. I. 2nd floor Eastside deck area.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/3/2024 (12:30 - 2:30) | 9/3/2024 (PM) | 09/03/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/03/2024
R. I. Conduits 3rd floor deck West side of the deck.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/11/2024 (8:00 - 10:00) | 9/11/2024 (AM) | 09/11/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/11/2024
R. I. 3rd East side deck for conduits in the concrete pour.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/20/2024 (8:00 - 10:00) | 9/20/2024 (AM) | 09/20/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/20/2024
R. I. 4th floor west end deck piping.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/27/2024 (8:00 - 10:00) | 9/27/2024 (AM) | 09/27/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/27/2024
4th floor east side deck pour.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/16/2024 (10:00 - 12:00) | 10/16/2024 (AM) | 10/16/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/16/2024
4th floor west side deck pour.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/28/2024 (12:30 - 2:30) | 10/28/2024 (PM) | 10/28/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/28/2024
Underground 1st floor in the dirt with PVC conduit.
Comment: They should be using a hot box for bending the conduits, a torch is burning and scorching the PVC conduits.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 11/14/2024 (Morning) | 11/14/2024 (AM) | 11/14/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/14/2024
Underground 1st floor office building.
|
||||
| Electrical Rough-in Inspection | Passed | 12/13/2024 (8:00 - 10:00) | 12/13/2024 (AM) | 12/13/2024 |
|
Corrections:
Miscellaneous/Other
Outstanding
12/13/2024
RIVisual ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 1/17/2025 (10:00 - 12:00) | 1/17/2025 (AM) | 01/17/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
01/17/2025
2nd and 3rd floor Ri 1-17-2025 ok
There a couple loose ends SE corner near stairs ( framing and some changes) that Todd from Gephart will get us back for.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 2/4/2025 (Morning) | 2/4/2025 (AM) | 02/04/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
02/19/2025
2nd and 3rd floor Ri 1-17-2025 ok
There a couple loose ends SE corner near stairs ( framing and some changes) that Todd from Gephart will get us back for.
|
||||
|
Miscellaneous/Other
Comment Only
02/04/2025
3 rd floor wall ri
|
||||
| Electrical Rough-in Inspection | Partial Pass | 2/25/2025 (Afternoon) | 2/25/2025 (PM) | 02/25/2025 |
| Second level ceiling inspection & 4th floor rough-in | ||||
|
Corrections:
Miscellaneous/Other
Outstanding
02/25/2025
4th floor walls
2nd floor ceilings
Ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 3/18/2025 (Morning) | 3/18/2025 (AM) | 03/18/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
03/18/2025
2nd and 3rd floor Ri 1-17-2025 ok
There a couple loose ends SE corner near stairs ( framing and some changes) that Todd from Gephart will get us back for.
|
||||
|
Miscellaneous/Other
Carried Forward
03/18/2025
3-18-25
1st floor RI OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 4/11/2025 (8:00 - 10:00) | 4/11/2025 (AM) | 04/11/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/11/2025
Bathroom lighting RI OK. 4th floor pendant lighting OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 4/25/2025 (10:00 - 12:00) | 4/25/2025 (AM) | 04/25/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/25/2025
New 3000 amp service OK. Transformer OK. Ready for hookup
|
||||
| Electrical Rough-in Inspection | Partial Pass | 5/19/2025 (10:00 - 12:00) | 5/19/2025 (AM) | 05/19/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/19/2025
2nd floor ceiling inspection OK
Checked in on parking ramp for lighting. OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/9/2025 (8:00 - 10:00) | 6/9/2025 (AM) | 06/09/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/09/2025
3rd floor ceiling RI OK
Checked Elevator UPS system for automatic transfer. OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/24/2025 (8:00 - 10:00) | 6/24/2025 (AM) | 06/24/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/24/2025
1st floor RI for a few new walls - OK
Beginning of underground work. Will follow up
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/30/2025 (12:30 - 2:30) | 6/30/2025 (PM) | 06/30/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/30/2025
1st floor RI and underground - OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/18/2025 (8:00 - 10:00) | 7/18/2025 (AM) | 07/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/18/2025
7/16 - underground for parking lot lights- OK
|
||||
| Electrical Rough-in Inspection | Passed | 8/29/2025 (10:00 - 12:00) | 8/29/2025 (AM) | 08/29/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/29/2025
All RI complete.
|
||||
| Electrical Final Inspection | Partial Pass | 8/29/2025 (12:30 - 2:30) | 8/29/2025 (PM) | 08/29/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/29/2025
Partial Final for temp CO.
Tested generator and all EM lighting.
Looked at all kitchen equipment.
Looked at all RTUs for OCP.
Did a full walkthrough but there is still work to be completed for final.
|
||||
| Electrical Final Inspection | Passed | 10/23/2025 (12:30 - 2:30) | 10/23/2025 (PM) | 10/23/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/23/2025
Final for SICK office buildout. OK
All panel schedules have been checked for available fault current calculations and arc flash protection stickers.
All receptacles and equipment have been tested and are functional.
10/23/25 Final for SICK
|
||||