PREL202409882
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Partial Pass | 9/11/2024 (8:00 - 10:00) | 9/11/2024 (AM) | 09/11/2024 |
Corrections:
Miscellaneous/Other
Comment Only
09/11/2024
Questions on site.
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/23/2024 (12:30 - 2:30) | 9/23/2024 (PM) | 09/23/2024 |
Corrections:
Miscellaneous/Other
Comment Only
09/23/2024
R. I. Light poles underground conduits.
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/24/2024 (Morning) | 9/24/2024 (AM) | 09/24/2024 |
Corrections:
Miscellaneous/Other
Comment Only
09/24/2024
R. I. Underground service- Ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/2/2024 (8:00 - 10:00) | 10/2/2024 (AM) | 10/02/2024 |
Corrections:
Miscellaneous/Other
Comment Only
10/02/2024
R. I. Room 426 for a mock up for inspections going forward.
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/8/2024 (Afternoon) | 10/8/2024 (PM) | 10/08/2024 |
Corrections:
Miscellaneous/Other
Comment Only
10/08/2024
R. I. Walls and ceilings rooms 415-427 - 13 rooms on 4th floor Area A.
|
||||
Progress Inspection | Partial Pass | 10/15/2024 (Afternoon) | 10/15/2024 (PM) | 10/15/2024 |
Corrections:
Miscellaneous/Other
Comment Only
10/15/2024
R. I. Area 4th floor- 4B - rooms 401-414.
|
||||
Progress Inspection | Partial Pass | 10/22/2024 (Afternoon) | 10/22/2024 (PM) | 10/22/2024 |
Corrections:
Miscellaneous/Other
Comment Only
10/22/2024
R. I. 13 Rooms 3rd floor 315-327.
|
||||
Progress Inspection | Partial Pass | 10/29/2024 (10:00 - 12:00) | 10/29/2024 (AM) | 10/29/2024 |
Corrections:
Miscellaneous/Other
Comment Only
10/29/2024
R. I. Area 3B rooms 301-314.
Looked at stairwells going from 1st to 4th floor.
Looked at the switch gear in the garage level.
Still need to ground to the water meter at the other end on the garage.
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/5/2024 (12:30 - 2:30) | 11/5/2024 (PM) | 11/05/2024 |
Corrections:
Miscellaneous/Other
Comment Only
11/05/2024
R. I. 2nd floor rooms 201-227 - Ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/12/2024 (Afternoon) | 11/12/2024 (PM) | 11/12/2024 |
Corrections:
Miscellaneous/Other
Comment Only
11/12/2024
R. I. 1st floor 22 units.
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/19/2024 (12:30 - 2:30) | 11/19/2024 (PM) | 11/19/2024 |
Corrections:
Miscellaneous/Other
Comment Only
11/19/2024
R. I. For 1st floor common areas.
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/8/2025 (Morning) | 1/8/2025 (AM) | 01/08/2025 |
Corrections:
Miscellaneous/Other
Comment Only
01/08/2025
Hard lid 1st floor common areas
|
||||
Electrical Final Inspection | Passed | 3/12/2025 (Morning) | 3/12/2025 (AM) | 03/13/2025 |
Corrections:
Miscellaneous/Other
Resolved
03/13/2025
426- need receptacle outside installed
406- need arc and gfi breakers swapped
Skydeck receptacles need gfci
Fire alarm breaker needs to be lock on
Boiler in park gar needs disconnect
3 Sumps need gfci protection
|
||||
Electrical Final Inspection | Passed | 03/20/2025 | ||
3/4 inspection CANCELED. vm 3/3/25 | ||||
Electrical Final Inspection | Passed | 2/25/2025 (Morning) | 2/25/2025 (AM) | 03/20/2025 |
Corrections:
Miscellaneous/Other
Resolved
03/20/2025
2 nd and 1st floor unit finals
Not all- some we could not get onto balconies
|
||||
Electrical Final Inspection | Passed | 3/5/2025 (Morning) | 3/5/2025 (AM) | 03/20/2025 |
Corrections:
Miscellaneous/Other
Resolved
03/20/2025
3-5-25
1,2,3 and 4th floor unit finals
Going back to all floors - final some units and some just needed balcony receptacles checked because they recently installed the balconies.
|
||||
Electrical Final Inspection | Passed | 2/26/2025 (Morning) | 2/26/2025 (AM) | 03/20/2025 |
Corrections:
Miscellaneous/Other
Resolved
03/20/2025
2-26-25
Finaled some units on all 4 floors
|
||||
Electrical Final Inspection | Passed | 2/12/2025 (Morning) | 2/12/2025 (AM) | 03/20/2025 |
4th finish-inspecting 12 units | ||||
Corrections:
Miscellaneous/Other
Resolved
03/20/2025
4th floor partial final
|
||||
Electrical Final Inspection | Passed | 2/19/2025 (Morning) | 2/19/2025 (AM) | 03/20/2025 |
Corrections:
Miscellaneous/Other
Resolved
03/20/2025
Partial 3 rd and 2 nd floor unit finals
|
||||
Electrical Final Inspection | Passed | 2/18/2025 (Morning) | 2/18/2025 (AM) | 03/20/2025 |
Corrections:
Miscellaneous/Other
Resolved
03/20/2025
2-18-25
4 th floor finals
|
||||
Progress Inspection | Passed | 03/20/2025 |