PREL202411025
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Underground Electrical Inspection | Partial Pass | 2/11/2025 (Afternoon) | 2/11/2025 (PM) | 02/11/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/11/2025
Underground ri
|
||||
| Electrical Rough-in Inspection | Partial Pass | 4/23/2025 (8:00 - 10:00) | 4/23/2025 (AM) | 04/23/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/23/2025
Wall ri
Stat and fire permit needed
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/8/2025 | 9/8/2025 (AM) | 09/08/2025 |
| Electrical Rough-in Inspection | Partial Pass | 9/16/2025 (10:00 - 12:00) | 9/16/2025 (AM) | 09/16/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/16/2025
Dry storage ri
|
||||
| Electrical Rough-in Inspection | Failed | 10/24/2025 (10:00 - 12:00) | 10/24/2025 (AM) | 10/24/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/24/2025
Ceiling inspection failed - do not pass with temporary wiring and lights above ceiling
|
||||
| Above Ceiling Inspection | Passed | 10/30/2025 (10:00 - 12:00) | 10/30/2025 (AM) | 10/30/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/30/2025
Ceiling ri
|
||||
| Underground Electrical Inspection | Passed | 12/10/2025 (2:30 - 3:30) | 12/10/2025 (PM) | 12/10/2025 |
| Electrical Final Inspection | Passed | 12/10/2025 (2:30 - 3:30) | 12/10/2025 (PM) | 12/10/2025 |
| Electrical Rough-in Inspection | Passed | 12/10/2025 (2:30 - 3:30) | 12/10/2025 (PM) | 12/10/2025 |