Permit Application Status

PREL202415668


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202415668
Electrical
Finaled
700 AMERICAN LLLP
Alteration/Repair/Replace
Complete electrical systems for 128-unit apt bldg; including wiring for temperature control and fire alarm
11/27/2024
01/08/2025
06/20/2026

Locations

Permits

Permit Number: PREL202415668

Electrical
Finaled
01/08/2025
06/20/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 2/5/2025 (Afternoon) 2/5/2025 (PM) 02/06/2025
Corrections:


Miscellaneous/Other
Outstanding
02/06/2025
Visual inspection of BBC sleeves going through concrete wall -ok 2-6-25

Electrical Rough-in Inspection Not Ready 2/11/2025 (Morning) 2/11/2025 (AM) 02/11/2025
Corrections:


Miscellaneous/Other
Carried Forward
02/11/2025
Call from Corey- not ready 2-11-25

Electrical Rough-in Inspection Not Ready 2/19/2025 (Afternoon) 2/19/2025 (PM) 02/19/2025
Electrical Rough-in Inspection Partial Pass 2/25/2025 (12:30 - 2:30) 2/25/2025 (PM) 02/25/2025
Corrections:


Miscellaneous/Other
Outstanding
02/25/2025
2-25-25 conduit inspection before concrete pour

Electrical Final Inspection Partial Pass 3/10/2025 (PM) 03/14/2025
Corrections:


Miscellaneous/Other
Carried Forward
03/14/2025
Island pvc. Pipes picture sent 3-10-25

Underground Electrical Inspection Passed 4/1/2025 (12:30 - 2:30) 4/1/2025 (PM) 04/01/2025
Electrical Rough-in Inspection Partial Pass 4/29/2025 (8:00 - 10:00) 4/29/2025 (AM) 04/29/2025
Corrections:


Miscellaneous/Other
Comment Only
04/29/2025
4-29-25 Meeting with electrician

Underground Electrical Inspection Partial Pass 5/19/2025 (2:30 - 3:30) 5/19/2025 (PM) 05/19/2025
Corrections:


Miscellaneous/Other
Comment Only
05/19/2025
Underground to transformer and generator-ok

Electrical Rough-in Inspection Partial Pass 6/16/2025 (10:00 - 12:00) 6/16/2025 (AM) 06/16/2025
Corrections:


Miscellaneous/Other
Carried Forward
06/16/2025
Elevator shaft inspection. X 2 Ok

Electrical Rough-in Inspection Partial Pass 6/24/2025 (8:00 - 10:00) 6/24/2025 (AM) 06/24/2025
Corrections:


Miscellaneous/Other
Outstanding
06/16/2025
Elevator shaft inspection. X 2 Ok

Miscellaneous/Other
Outstanding
06/24/2025
6-24-25 5th floor- unit and corridor RI from unit 517 and west Unit 503 RI also on the east side

Electrical Rough-in Inspection Partial Pass 6/30/2025 (10:00 - 12:00) 6/30/2025 (AM) 06/30/2025
Corrections:


Miscellaneous/Other
Carried Forward
07/01/2025
The remaining units on 5 th floor and corridors. 1 st and 4 th floor west electrical rooms ceiling and walls.

Electrical Rough-in Inspection Partial Pass 7/2/2025 (12:30 - 2:30) 7/2/2025 (PM) 07/02/2025
4th floor-14units
Corrections:


Miscellaneous/Other
Carried Forward
07/08/2025
The remaining units on 5 th floor and corridors. 1 st and 4 th floor west electrical rooms ceiling and walls.

Miscellaneous/Other
Carried Forward
07/08/2025
7-2-25 West half 4th floor units and corridors Look at CT cab before Xcel installs meter and powers up

Electrical Rough-in Inspection Partial Pass 7/14/2025 (2:30 - 3:30) 7/14/2025 (PM) 07/14/2025
Corrections:


Miscellaneous/Other
Carried Forward
07/15/2025
The remaining units on 5 th floor and corridors. 1 st and 4 th floor west electrical rooms ceiling and walls.

Miscellaneous/Other
Carried Forward
07/15/2025
7-2-25 West half 4th floor units and corridors Look at CT cab before Xcel installs meter and powers up

Miscellaneous/Other
Comment Only
07/14/2025
East half of 4 th floor units RI ( 401 - 414) and corridors Landings RI. - east side 5 th 4 th and 3rd floor West all landings Ri (1-5)

Electrical Rough-in Inspection Partial Pass 7/16/2025 (8:00 - 10:00) 7/16/2025 (AM) 07/16/2025
Corrections:


Miscellaneous/Other
Carried Forward
07/17/2025
7-16-25 Service ok

Electrical Rough-in Inspection Partial Pass 7/22/2025 (8:00 - 10:00) 7/22/2025 (AM) 07/22/2025
14 Units
Corrections:


Miscellaneous/Other
Outstanding
07/15/2025
The remaining units on 5 th floor and corridors. 1 st and 4 th floor west electrical rooms ceiling and walls.

Miscellaneous/Other
Outstanding
07/15/2025
7-2-25 West half 4th floor units and corridors Look at CT cab before Xcel installs meter and powers up

Miscellaneous/Other
Outstanding
07/22/2025
7-22-25 West half of 3 rd floor unit Ri Meter banks first and second d floor

Miscellaneous/Other
Outstanding
07/28/2025
East half of 3 rd floor units and corridors 7-28-25

Electrical Rough-in Inspection Partial Pass 7/23/2025 (2:30 - 3:30) 7/23/2025 (PM) 07/23/2025
Corrections:


Miscellaneous/Other
Carried Forward
07/23/2025
7-16-25 Service ok

Miscellaneous/Other
Carried Forward
07/23/2025
7-23-25 Underground for exterior lights

Electrical Rough-in Inspection Partial Pass 7/28/2025 (2:30 - 3:30) 7/28/2025 (PM) 07/28/2025
Corrections:


Miscellaneous/Other
Outstanding
07/23/2025
7-16-25 Service ok

Miscellaneous/Other
Outstanding
07/23/2025
7-23-25 Underground for exterior lights

Miscellaneous/Other
Outstanding
07/28/2025
7-28-25 East half of 3 rd floor units and corridors

Electrical Rough-in Inspection Partial Pass 8/4/2025 (2:30 - 3:30) 8/4/2025 (PM) 08/04/2025
2nd floor-14 units
Corrections:


Miscellaneous/Other
Carried Forward
08/05/2025
West half of 2nd floor units and corridors RI-OK

Electrical Rough-in Inspection Partial Pass 8/11/2025 (2:30 - 3:30) 8/11/2025 (PM) 08/11/2025
Corrections:


Miscellaneous/Other
Carried Forward
08/12/2025
West half of 2nd floor units and corridors RI-OK

Miscellaneous/Other
Carried Forward
08/12/2025
8-11-25 East half of 2nd floor units and corridors RI

Electrical Rough-in Inspection Partial Pass 8/18/2025 (2:30 - 3:30) 8/18/2025 (PM) 08/18/2025
Corrections:


Miscellaneous/Other
Carried Forward
08/19/2025
West half of 2nd floor units and corridors RI-OK

Miscellaneous/Other
Carried Forward
08/19/2025
8-11-25 East half of 2nd floor units and corridors RI

Miscellaneous/Other
Carried Forward
08/19/2025
8-18-25 West half of first floor u its and corridors Ceiling on 1st floor corridors to be drop ceiling - will need a ceiling inspection

Electrical Rough-in Inspection Partial Pass 8/25/2025 (2:30 - 3:30) 8/25/2025 (PM) 08/25/2025
Corrections:


Miscellaneous/Other
Carried Forward
08/26/2025
West half of 2nd floor units and corridors RI-OK

Miscellaneous/Other
Carried Forward
08/26/2025
8-11-25 East half of 2nd floor units and corridors RI

Miscellaneous/Other
Carried Forward
08/26/2025
8-18-25 West half of first floor u its and corridors Ceiling on 1st floor corridors to be drop ceiling - will need a ceiling inspection

Miscellaneous/Other
Carried Forward
08/26/2025
8-25-25 East half of 1st floor- units and corridors-ok

Electrical Rough-in Inspection Partial Pass 8/28/2025 (12:30 - 2:30) 8/28/2025 (PM) 08/28/2025
Corrections:


Miscellaneous/Other
Outstanding
08/26/2025
West half of 2nd floor units and corridors RI-OK

Miscellaneous/Other
Outstanding
08/26/2025
8-11-25 East half of 2nd floor units and corridors RI

Miscellaneous/Other
Outstanding
08/26/2025
8-18-25 West half of first floor u its and corridors Ceiling on 1st floor corridors to be drop ceiling - will need a ceiling inspection

Miscellaneous/Other
Outstanding
08/26/2025
8-25-25 East half of 1st floor- units and corridors-ok

Miscellaneous/Other
Outstanding
08/28/2025
8-28-25 Commons area- exterior walls only RI-ok

Electrical Rough-in Inspection Partial Pass 9/2/2025 (2:30 - 3:30) 9/2/2025 (PM) 09/03/2025
Corrections:


Miscellaneous/Other
Outstanding
09/03/2025
9-3-25 Parking ramp ceiling spray foam area and adjacent area

Electrical Rough-in Inspection Partial Pass 9/4/2025 (2:30 - 3:30) 9/4/2025 (PM) 09/04/2025
Commons area
Corrections:


Miscellaneous/Other
Outstanding
09/04/2025
9-4-25 Future retail space exterior wall RI

Electrical Rough-in Inspection Partial Pass 9/8/2025 (2:30 - 3:30) 9/8/2025 (PM) 09/08/2025
Corrections:


Miscellaneous/Other
Carried Forward
09/08/2025
Hard lid areas of commons space

Miscellaneous/Other
Outstanding
09/11/2025
Interior walls of common space- OK 9-11-25

Electrical Rough-in Inspection Partial Pass 9/11/2025 (10:00 - 12:00) 9/11/2025 (AM) 09/11/2025
Corrections:


Miscellaneous/Other
Carried Forward
09/16/2025
Hard lid areas of commons space

Miscellaneous/Other
Carried Forward
09/16/2025
interior walls of commons area 9-11-25

Electrical Rough-in Inspection Partial Pass 9/18/2025 (8:00 - 10:00) 9/18/2025 (AM) 09/18/2025
Corrections:


Miscellaneous/Other
Outstanding
09/16/2025
Hard lid areas of commons space

Miscellaneous/Other
Outstanding
09/16/2025
interior walls of commons area 9-11-25

Miscellaneous/Other
Outstanding
09/18/2025
Commons area ceiling RI 1st floor hallway ceiling RI ok 9-18-25

Progress Inspection Partial Pass 9/30/2025 (8:00 - 10:00) 9/30/2025 (AM) 09/30/2025
Corrections:


Miscellaneous/Other
Carried Forward
09/30/2025
5th floor unit finals only 9-30-25 Need pic of unit 520 bath gfci

Electrical Final Inspection Partial Pass 10/7/2025 (12:30 - 2:30) 10/7/2025 (PM) 10/07/2025
Corrections:


Miscellaneous/Other
Outstanding
03/14/2025
Island pvc. Pipes picture sent 3-10-25

Miscellaneous/Other
Outstanding
10/07/2025
Fourth floor unit finals-Except unit 401 10-7-2025

Progress Inspection Partial Pass 10/28/2025 (10:00 - 12:00) 10/28/2025 (AM) 10/28/2025
Corrections:


Miscellaneous/Other
Comment Only
10/28/2025
3rd floor unit finals except unit 326 and unit 426 final

Electrical Final Inspection Partial Pass 11/06/2025
Corrections:


Miscellaneous/Other
Comment Only
11/06/2025
2nd floor unit finals all except unit #226

Progress Inspection Partial Pass 11/6/2025 (8:00 - 10:00) 11/6/2025 (AM) 11/06/2025
Corrections:


Miscellaneous/Other
Comment Only
11/06/2025
Second floor unit finals-all except unit 226

Electrical Final Inspection Partial Pass 12/10/2025 (12:30 - 2:30) 12/10/2025 (PM) 12/10/2025
Corrections:


Miscellaneous/Other
Outstanding
12/10/2025
12-10-2025 1- misc lights missing in commons space 2- need 123 final 3- need 111 island wiring 4- need 109 final 5- Need to Look at Max breakers for mini splits and ac cond..Need to be labeled 6- Verify Tesla EV charger amps. Units say 48amps, breakers are 40 amp 7- Dryer GFCI protection-located in maintenance room Still need to look at rooftops and all exterior electrical

Miscellaneous/Other
Comment Only
12/10/2025
12-10-2025 Did unit finals 226,326,401

Lighting Inspection Sign Passed 12/11/2025
Electrical Final Inspection Partial Pass 12/17/2025 (2:30 - 3:30) 12/17/2025 (PM) 12/17/2025
Corrections:


Miscellaneous/Other
Comment Only
12/17/2025
Inspection date of 12-12-25- 1st floor corridor- ok except furnace flex conduit needs a strap 2nd floor corridor- ok except receptacle near elevator not working 4th floor corridor-ok 5th floor corridor -ok unit 123-ok

Miscellaneous/Other
Comment Only
12/17/2025
Inspections 12-15-2025 and 12-16-2025 and 12-17-2025 unit 109-ok Clothes dryer in parking garage-needed gfci-done Checked MOP of mini splits and condensers in parking garage unit 111 was ok except island power. now done on 12-17 Check rooftop MOP- ok Roof top exhaust fans in use covers were in the face up position. Electrician moved them. 12-17 Rooftop conduits needed straps-done 12-17 Sump and ejector pumps in garage needed GFCI protection-done 12-17 Checked all exterior receptacles-ok 12-16-2025 Needed multiple breaker locks-fan coil units and some furnaces-done 12-17 Garage fans that were plugged in needed GFCI protection-done 12-17 Vestibule heaters needed disconnects- some had shutoffs on units, others needed breaker locks 12-17 Kitchen in commons area needed GFCI protection for receptacle to right of sink and pop up receptacle-done 12-17 Coffee area receptacle needed GFCI protection-done 12-16 Generator needed Disconnect label-done 12-17 garage receptacle near stairs and elevator needed gfci protection-done 12-16 3rd floor corridor-ok 12-17

Miscellaneous/Other
Carried Forward
12/17/2025
12-17-2025 need FA red breaker lock on Sign circuit labeled and a breaker lock installed Expecting pictures early morning of 12-18-2025

Miscellaneous/Other
Carried Forward
12/17/2025
Need tesla chargers to be adjusted for a 40 amp circuit. General contractor is responsible for this since they are in control of the app. General contractor is responsible for the addition of a ballard in garage to protect electrical panel.

Electrical Final Inspection Partial Pass 12/18/2025
Corrections:


Miscellaneous/Other
Carried Forward
12/18/2025
12-17-2025 need FA red breaker lock on Sign circuit labeled and a breaker lock installed Expecting pictures early morning of 12-18-2025

Miscellaneous/Other
Carried Forward
12/18/2025
Need tesla chargers to be adjusted for a 40 amp circuit. General contractor is responsible for this since they are in control of the app. General contractor is responsible for the addition of a ballard in garage to protect electrical panel.

Miscellaneous/Other
Comment Only
12/18/2025
Pictures received 12-18-2025 Sign circuit labeled and breaker lock installed Red breaker lock on for Fire Alarm is installed

Electrical Final Inspection Passed 12/22/2025
Corrections:


Miscellaneous/Other
Resolved
12/22/2025
12-17-2025 need FA red breaker lock on Sign circuit labeled and a breaker lock installed Expecting pictures early morning of 12-18-2025

Miscellaneous/Other
Outstanding
12/18/2025
Need tesla chargers to be adjusted for a 40 amp circuit. General contractor is responsible for this since they are in control of the app. General contractor is responsible for the addition of a ballard in garage to protect electrical panel.

Miscellaneous/Other
Comment Only
12/22/2025
Bollard was installed to protect the electrical panel in the parking garage. Tesla chargers that were fused at 40 amps were configured in the tesla app to only draw 32 amps