PREL202415668
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Partial Pass | 2/5/2025 (Afternoon) | 2/5/2025 (PM) | 02/06/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
02/06/2025
Visual inspection of BBC sleeves going through concrete wall -ok
2-6-25
|
||||
| Electrical Rough-in Inspection | Not Ready | 2/11/2025 (Morning) | 2/11/2025 (AM) | 02/11/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
02/11/2025
Call from Corey- not ready 2-11-25
|
||||
| Electrical Rough-in Inspection | Not Ready | 2/19/2025 (Afternoon) | 2/19/2025 (PM) | 02/19/2025 |
| Electrical Rough-in Inspection | Partial Pass | 2/25/2025 (12:30 - 2:30) | 2/25/2025 (PM) | 02/25/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
02/25/2025
2-25-25 conduit inspection before concrete pour
|
||||
| Electrical Final Inspection | Partial Pass | 3/10/2025 (PM) | 03/14/2025 | |
|
Corrections:
Miscellaneous/Other
Carried Forward
03/14/2025
Island pvc. Pipes picture sent 3-10-25
|
||||
| Underground Electrical Inspection | Passed | 4/1/2025 (12:30 - 2:30) | 4/1/2025 (PM) | 04/01/2025 |
| Electrical Rough-in Inspection | Partial Pass | 4/29/2025 (8:00 - 10:00) | 4/29/2025 (AM) | 04/29/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/29/2025
4-29-25
Meeting with electrician
|
||||
| Underground Electrical Inspection | Partial Pass | 5/19/2025 (2:30 - 3:30) | 5/19/2025 (PM) | 05/19/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/19/2025
Underground to transformer and generator-ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/16/2025 (10:00 - 12:00) | 6/16/2025 (AM) | 06/16/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
06/16/2025
Elevator shaft inspection. X 2
Ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/24/2025 (8:00 - 10:00) | 6/24/2025 (AM) | 06/24/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
06/16/2025
Elevator shaft inspection. X 2
Ok
|
||||
|
Miscellaneous/Other
Outstanding
06/24/2025
6-24-25
5th floor- unit and corridor RI from unit 517 and west
Unit 503 RI also on the east side
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/30/2025 (10:00 - 12:00) | 6/30/2025 (AM) | 06/30/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/01/2025
The remaining units on 5 th floor and corridors.
1 st and 4 th floor west electrical rooms ceiling and walls.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/2/2025 (12:30 - 2:30) | 7/2/2025 (PM) | 07/02/2025 |
| 4th floor-14units | ||||
|
Corrections:
Miscellaneous/Other
Carried Forward
07/08/2025
The remaining units on 5 th floor and corridors.
1 st and 4 th floor west electrical rooms ceiling and walls.
|
||||
|
Miscellaneous/Other
Carried Forward
07/08/2025
7-2-25
West half 4th floor units and corridors
Look at CT cab before Xcel installs meter and powers up
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/14/2025 (2:30 - 3:30) | 7/14/2025 (PM) | 07/14/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/15/2025
The remaining units on 5 th floor and corridors.
1 st and 4 th floor west electrical rooms ceiling and walls.
|
||||
|
Miscellaneous/Other
Carried Forward
07/15/2025
7-2-25
West half 4th floor units and corridors
Look at CT cab before Xcel installs meter and powers up
|
||||
|
Miscellaneous/Other
Comment Only
07/14/2025
East half of 4 th floor units RI ( 401 - 414) and corridors
Landings RI. - east side 5 th 4 th and 3rd floor
West all landings Ri (1-5)
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/16/2025 (8:00 - 10:00) | 7/16/2025 (AM) | 07/16/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/17/2025
7-16-25
Service ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/22/2025 (8:00 - 10:00) | 7/22/2025 (AM) | 07/22/2025 |
| 14 Units | ||||
|
Corrections:
Miscellaneous/Other
Outstanding
07/15/2025
The remaining units on 5 th floor and corridors.
1 st and 4 th floor west electrical rooms ceiling and walls.
|
||||
|
Miscellaneous/Other
Outstanding
07/15/2025
7-2-25
West half 4th floor units and corridors
Look at CT cab before Xcel installs meter and powers up
|
||||
|
Miscellaneous/Other
Outstanding
07/22/2025
7-22-25
West half of 3 rd floor unit Ri
Meter banks first and second d floor
|
||||
|
Miscellaneous/Other
Outstanding
07/28/2025
East half of 3 rd floor units and corridors
7-28-25
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/23/2025 (2:30 - 3:30) | 7/23/2025 (PM) | 07/23/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/23/2025
7-16-25
Service ok
|
||||
|
Miscellaneous/Other
Carried Forward
07/23/2025
7-23-25
Underground for exterior lights
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/28/2025 (2:30 - 3:30) | 7/28/2025 (PM) | 07/28/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
07/23/2025
7-16-25
Service ok
|
||||
|
Miscellaneous/Other
Outstanding
07/23/2025
7-23-25
Underground for exterior lights
|
||||
|
Miscellaneous/Other
Outstanding
07/28/2025
7-28-25
East half of
3 rd floor units and corridors
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/4/2025 (2:30 - 3:30) | 8/4/2025 (PM) | 08/04/2025 |
| 2nd floor-14 units | ||||
|
Corrections:
Miscellaneous/Other
Carried Forward
08/05/2025
West half of 2nd floor units and corridors RI-OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/11/2025 (2:30 - 3:30) | 8/11/2025 (PM) | 08/11/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
08/12/2025
West half of 2nd floor units and corridors RI-OK
|
||||
|
Miscellaneous/Other
Carried Forward
08/12/2025
8-11-25
East half of 2nd floor units and corridors RI
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/18/2025 (2:30 - 3:30) | 8/18/2025 (PM) | 08/18/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
08/19/2025
West half of 2nd floor units and corridors RI-OK
|
||||
|
Miscellaneous/Other
Carried Forward
08/19/2025
8-11-25
East half of 2nd floor units and corridors RI
|
||||
|
Miscellaneous/Other
Carried Forward
08/19/2025
8-18-25
West half of first floor u its and corridors
Ceiling on 1st floor corridors to be drop ceiling - will need a ceiling inspection
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/25/2025 (2:30 - 3:30) | 8/25/2025 (PM) | 08/25/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
08/26/2025
West half of 2nd floor units and corridors RI-OK
|
||||
|
Miscellaneous/Other
Carried Forward
08/26/2025
8-11-25
East half of 2nd floor units and corridors RI
|
||||
|
Miscellaneous/Other
Carried Forward
08/26/2025
8-18-25
West half of first floor u its and corridors
Ceiling on 1st floor corridors to be drop ceiling - will need a ceiling inspection
|
||||
|
Miscellaneous/Other
Carried Forward
08/26/2025
8-25-25
East half of 1st floor- units and corridors-ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/28/2025 (12:30 - 2:30) | 8/28/2025 (PM) | 08/28/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/26/2025
West half of 2nd floor units and corridors RI-OK
|
||||
|
Miscellaneous/Other
Outstanding
08/26/2025
8-11-25
East half of 2nd floor units and corridors RI
|
||||
|
Miscellaneous/Other
Outstanding
08/26/2025
8-18-25
West half of first floor u its and corridors
Ceiling on 1st floor corridors to be drop ceiling - will need a ceiling inspection
|
||||
|
Miscellaneous/Other
Outstanding
08/26/2025
8-25-25
East half of 1st floor- units and corridors-ok
|
||||
|
Miscellaneous/Other
Outstanding
08/28/2025
8-28-25
Commons area- exterior walls only RI-ok
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/2/2025 (2:30 - 3:30) | 9/2/2025 (PM) | 09/03/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
09/03/2025
9-3-25
Parking ramp ceiling spray foam area and adjacent area
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/4/2025 (2:30 - 3:30) | 9/4/2025 (PM) | 09/04/2025 |
| Commons area | ||||
|
Corrections:
Miscellaneous/Other
Outstanding
09/04/2025
9-4-25
Future retail space exterior wall RI
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/8/2025 (2:30 - 3:30) | 9/8/2025 (PM) | 09/08/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
09/08/2025
Hard lid areas of commons space
|
||||
|
Miscellaneous/Other
Outstanding
09/11/2025
Interior walls of common space- OK 9-11-25
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/11/2025 (10:00 - 12:00) | 9/11/2025 (AM) | 09/11/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
09/16/2025
Hard lid areas of commons space
|
||||
|
Miscellaneous/Other
Carried Forward
09/16/2025
interior walls of commons area 9-11-25
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/18/2025 (8:00 - 10:00) | 9/18/2025 (AM) | 09/18/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
09/16/2025
Hard lid areas of commons space
|
||||
|
Miscellaneous/Other
Outstanding
09/16/2025
interior walls of commons area 9-11-25
|
||||
|
Miscellaneous/Other
Outstanding
09/18/2025
Commons area ceiling RI
1st floor hallway ceiling RI ok
9-18-25
|
||||
| Progress Inspection | Partial Pass | 9/30/2025 (8:00 - 10:00) | 9/30/2025 (AM) | 09/30/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
09/30/2025
5th floor unit finals only 9-30-25
Need pic of unit 520 bath gfci
|
||||
| Electrical Final Inspection | Partial Pass | 10/7/2025 (12:30 - 2:30) | 10/7/2025 (PM) | 10/07/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
03/14/2025
Island pvc. Pipes picture sent 3-10-25
|
||||
|
Miscellaneous/Other
Outstanding
10/07/2025
Fourth floor unit finals-Except unit 401
10-7-2025
|
||||
| Progress Inspection | Partial Pass | 10/28/2025 (10:00 - 12:00) | 10/28/2025 (AM) | 10/28/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/28/2025
3rd floor unit finals except unit 326
and unit 426 final
|
||||
| Electrical Final Inspection | Partial Pass | 11/06/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
11/06/2025
2nd floor unit finals all except unit #226
|
||||
| Progress Inspection | Partial Pass | 11/6/2025 (8:00 - 10:00) | 11/6/2025 (AM) | 11/06/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/06/2025
Second floor unit finals-all except unit 226
|
||||
| Electrical Final Inspection | Partial Pass | 12/10/2025 (12:30 - 2:30) | 12/10/2025 (PM) | 12/10/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
12/10/2025
12-10-2025
1- misc lights missing in commons space
2- need 123 final
3- need 111 island wiring
4- need 109 final
5- Need to Look at Max breakers for mini splits and ac cond..Need to be labeled
6- Verify Tesla EV charger amps. Units say 48amps, breakers are 40 amp
7- Dryer GFCI protection-located in maintenance room
Still need to look at rooftops and all exterior electrical
|
||||
|
Miscellaneous/Other
Comment Only
12/10/2025
12-10-2025
Did unit finals 226,326,401
|
||||
| Lighting Inspection Sign | Passed | 12/11/2025 | ||
| Electrical Final Inspection | Partial Pass | 12/17/2025 (2:30 - 3:30) | 12/17/2025 (PM) | 12/17/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/17/2025
Inspection date of 12-12-25-
1st floor corridor- ok except furnace flex conduit needs a strap
2nd floor corridor- ok except receptacle near elevator not working
4th floor corridor-ok
5th floor corridor -ok
unit 123-ok
|
||||
|
Miscellaneous/Other
Comment Only
12/17/2025
Inspections 12-15-2025 and 12-16-2025 and 12-17-2025
unit 109-ok
Clothes dryer in parking garage-needed gfci-done
Checked MOP of mini splits and condensers in parking garage
unit 111 was ok except island power. now done on 12-17
Check rooftop MOP- ok
Roof top exhaust fans in use covers were in the face up position. Electrician moved them. 12-17
Rooftop conduits needed straps-done 12-17
Sump and ejector pumps in garage needed GFCI protection-done 12-17
Checked all exterior receptacles-ok 12-16-2025
Needed multiple breaker locks-fan coil units and some furnaces-done 12-17
Garage fans that were plugged in needed GFCI protection-done 12-17
Vestibule heaters needed disconnects- some had shutoffs on units, others needed breaker locks 12-17
Kitchen in commons area needed GFCI protection for receptacle to right of sink and pop up receptacle-done 12-17
Coffee area receptacle needed GFCI protection-done 12-16
Generator needed Disconnect label-done 12-17
garage receptacle near stairs and elevator needed gfci protection-done 12-16
3rd floor corridor-ok 12-17
|
||||
|
Miscellaneous/Other
Carried Forward
12/17/2025
12-17-2025
need FA red breaker lock on
Sign circuit labeled and a breaker lock installed
Expecting pictures early morning of 12-18-2025
|
||||
|
Miscellaneous/Other
Carried Forward
12/17/2025
Need tesla chargers to be adjusted for a 40 amp circuit. General contractor is responsible for this since they are in control of the app.
General contractor is responsible for the addition of a ballard in garage to protect electrical panel.
|
||||
| Electrical Final Inspection | Partial Pass | 12/18/2025 | ||
|
Corrections:
Miscellaneous/Other
Carried Forward
12/18/2025
12-17-2025
need FA red breaker lock on
Sign circuit labeled and a breaker lock installed
Expecting pictures early morning of 12-18-2025
|
||||
|
Miscellaneous/Other
Carried Forward
12/18/2025
Need tesla chargers to be adjusted for a 40 amp circuit. General contractor is responsible for this since they are in control of the app.
General contractor is responsible for the addition of a ballard in garage to protect electrical panel.
|
||||
|
Miscellaneous/Other
Comment Only
12/18/2025
Pictures received 12-18-2025
Sign circuit labeled and breaker lock installed
Red breaker lock on for Fire Alarm is installed
|
||||
| Electrical Final Inspection | Passed | 12/22/2025 | ||
|
Corrections:
Miscellaneous/Other
Resolved
12/22/2025
12-17-2025
need FA red breaker lock on
Sign circuit labeled and a breaker lock installed
Expecting pictures early morning of 12-18-2025
|
||||
|
Miscellaneous/Other
Outstanding
12/18/2025
Need tesla chargers to be adjusted for a 40 amp circuit. General contractor is responsible for this since they are in control of the app.
General contractor is responsible for the addition of a ballard in garage to protect electrical panel.
|
||||
|
Miscellaneous/Other
Comment Only
12/22/2025
Bollard was installed to protect the electrical panel in the parking garage.
Tesla chargers that were fused at 40 amps were configured in the tesla app to only draw 32 amps
|
||||